Re: Custom Code Maintenance Contract for IPM

daemon@ATHENA.MIT.EDU (Rocklyn E. Clarke)
Thu Apr 25 17:43:53 2002

Mime-Version: 1.0
Message-Id: <p05010408b8ee221f48ec@[18.152.2.129]>
In-Reply-To: <200204182036.QAA15590@pacific-carrier-annex.mit.edu>
Date: Thu, 25 Apr 2002 17:43:47 -0400
To: David F Lambert <LAMBERT@MITVMA.MIT.EDU>
From: "Rocklyn E. Clarke" <rclarke@MIT.EDU>
Cc: Enterprise Printing Delivery Project Team <printdel@MIT.EDU>,
        Roger A Roach <RAR@MIT.EDU>, Bob Ferrara <rferrara@MIT.EDU>,
        "Regan, Theresa M" <tregan@MIT.EDU>,
        "Higgins, Kenneth" <khiggins@MIT.EDU>
Content-Type: text/plain; charset="us-ascii" ; format="flowed"

Hi Dave,

By now you will have seen my email to IBM asking for an update on the 
status of the maintenance contract.  The initial contract was for 
$13425 broken down as follows:

  - $3750 - Initial fee
  - $9675 - 45 hours at $215/hr

Based on my own review (via SAPweb) of PO 5700001573, we appear to 
have paid IBM $6330 out of the $13425 (:

  - $3750 - Initial fee for the contract (10/25/2001)
  - $ 860 - 4 hours (1/23/2002)
  - $1720 - 8 hours (3/27/2002)

This should leave us with $7095 (33 billable hours) remaining on the 
contract.  I expect IBM's numbers to match these figures.

I did not put another $13425 for web interface maintenance in the 
EAST budget for FY2003.  This may have been because IPM was being 
removed from EAST's purview, in which case it would have been a 
partial oversight on my part.  Of course it may also have been a 
complete oversight on my part.

I suggest that we plan to spend another 12 billable hours by June 30 
and then carry forward the remaining 21 billable hours.  I would 
recommend that the contract be kept with EAST since this would be 
consistent with the currently emerging EAST business model (checkout 
http://web.mit.edu/east/www/).

Rocklyn


-------
At 4:33 PM -0400 4/18/02, David F Lambert wrote:
>Rocklyn,
>
>Your time here is getting short (get that silly grin off your face!).
>I'm concerned about the maintenance contract we have with the IBM
>folks in Boulder.  As you know, we're still occasionally finding
>things for IBM to do.
>
>How much of the $5K for FY02 is still available?  Did EAST budget
>for additional $5K for FY03?  Who do you envision managing this
>contract & related work after you're out of here?
>
>-Dave