[2031] in Enterprise Print Delivery Team
Re: Enterprise Print November Status Report
daemon@ATHENA.MIT.EDU (David F Lambert)
Mon Dec 10 17:48:34 2001
Message-Id: <200112102248.RAA01047@fort-point-station.mit.edu>
Date: Mon, 10 Dec 01 17:37:52 EST
From: David F Lambert <LAMBERT@MITVMA.MIT.EDU>
To: "Huxley, Bil" <huxley@MIT.EDU>,
Enterprise Printing Delivery Project Team <printdel@MIT.EDU>
cc: "Regan, Theresa M" <tregan@MIT.EDU>
In-Reply-To: Message of Mon, 10 Dec 2001 11:02:44 -0500 from <huxley@MIT.EDU>
Are you saying you expect our status reports to be accurate, Bil? ;-)
Yeah, it shoulda been on the goals list. As a subsequent email indicated,
we'd like to change the queue names to something a tad more meaningful -
and I do mean a tad. We're hoping DC for Data Center is more useful
to folks than EP. Since we've solved the simplex in and duplex out
issue, we should be able to add DC1 & DC12 queues as soon as folks
say okay to the new names.
-Dave
ps. I sometimes hedge on including goal items - trying to minimize too
many carryovers in subsequent reports. However, for the EP60/62 item
it was just bad memory... :(
On Mon, 10 Dec 2001 11:02:44 -0500 Bil said:
>Hi Dave,
>
>Since EP1 & FSS1 are listed as accomplishments in this past period,
>shouldn't EP60/EP62 be at least listed as a goal for the coming
>period? It's been an open request for a while now :)
>
>Thanks ,
> Bil
>
>At 12/10/2001 08:19 AM -0500, David F Lambert wrote:
>
>>Project Name: Enterprise Printing Delivery Project
>>Team Members: Mary Ellen Bushnell, Rocklyn Clarke, Lynne Durland &
>> Dave Lambert
>>Report Date: 12/10/2001
>>Project Notebook: http://web.mit.edu/is/delivery/enterprint/
>>
>>Accomplishments for the past period:
>>- Got banner & duplex/bounce working; worked with CAOTech to
>> implement KLPR on their desktops; and moved EP1 to IPM's control
>>- Wrote article for i/s Newsletter; continued building Stock Answers
>> and finetuning of enduser documentation
>>- Jody reinstalled Plunder in E40 and added the new disks to both
>> Pillage & Plunder
>>- Implemented FSS1 queue for future SAP testing by FSS
>>- Implemented General Ledger print queue restrictions
>>- Performed more sizing calculations based on CAO's request to print
>> GL at 600 dpi
>>- Worked with Graduate admissions office on submissions
>>- Worked with IBM to resolve a registration problem
>>- Received latest patches from IBM
>>- Worked with R3-Print and others to modify and clarify the process
>> for adding, deleting & changing SAP print queues
>>- Handed off Operator documentation to the DOST documentation team
>>- Handed off sysadmin web pages to Lynne for ongoing maintenance
>>
>>Goals for the coming period:
>>- Merge filter mods into single parameterized version of filter
>>- Reject klpr submissions when account number, building, or room are unknown
>>- Provide updated VM print accounting data for business model
>>- Set up cron job to issue monthly accounting reports
>>- Set up cron job to clean up filter logs
>>- Reinstall IPM licenses now that Plunder is available again
>>- Print the Monthly GL Statements if CAO is ready
>>- Get completed .htaccess mods in MIT Apache distribution (carryover)
>>- Wrap up Rocklyn's membership in Printdel (carryover)
>>- Continue to work on end user instructions (web pages) & add entries
>> to Stock Answers (ongoing)
>>- Publish article in i/s Newsletter
>>- Continue customer discussions wrt IPM rollout & network based
>> mainframe printing (ongoing)
>>
>>Issues:
>> ASST still needs resources besides Lynne to manage IPM post delivery.
>> Monthly GL Statement printing with IPM was postponed for another month
>> due to some unrelated feature testing required by CAO.
>>
>>Key learnings:
>> None
>>
>>Team dynamics:
>> Good
>>
>>Additional comments:
>> Recent efforts by ASST, R3-Print, CAOTech and others helped make for