Facilities MIS Strategic Planning Report, 3/24/1999

daemon@ATHENA.MIT.EDU (Tim McGovern)
Wed Mar 24 13:05:50 1999

Date: Wed, 24 Mar 1999 13:05:43 -0500
To: magellan@MIT.EDU
From: Tim McGovern <tjm@MIT.EDU>

Project Name:     Facilities-MIS Strategic Planning
Project Leaders:  Anne Whealan, Tim McGovern
Report Date:      Mar. 24, 1999
Project Notebook: http://web.mit.edu/is/discovery/plant-sp/

Accomplishments past period
-  Engaged a discussion with Facilities' Operational Leadership Team (OLT)
   around priorities given current budget realities.
-  Reviewed drafts in the planning team of some new sections for the report
   that address defects identified by various groups.

Goals for the coming period
-  Engage a discussion about structure & thrust of final report with
   representatives from Facilities' Strategic Leadership Team (SLT)
-  Continue to write/edit sections of the report to address the report's
   defects.

Issues
-  Nothing new this fortnight.  Meetings have become the project ;(.

Key learnings
-  Properly facilitated, any group can be helpful in brainstorming ways to
   proceed after you've overcome the shock of bad news.

Team dynamics
-  Planning team is holding together, in spite of the confusion induced by
   the budget letter.

Additional comments
-  Nothing.