Facilities MIS Strategic Planning Report, 3/24/1999
daemon@ATHENA.MIT.EDU (Tim McGovern)
Wed Mar 24 13:05:50 1999
Date: Wed, 24 Mar 1999 13:05:43 -0500
To: magellan@MIT.EDU
From: Tim McGovern <tjm@MIT.EDU>
Project Name: Facilities-MIS Strategic Planning
Project Leaders: Anne Whealan, Tim McGovern
Report Date: Mar. 24, 1999
Project Notebook: http://web.mit.edu/is/discovery/plant-sp/
Accomplishments past period
- Engaged a discussion with Facilities' Operational Leadership Team (OLT)
around priorities given current budget realities.
- Reviewed drafts in the planning team of some new sections for the report
that address defects identified by various groups.
Goals for the coming period
- Engage a discussion about structure & thrust of final report with
representatives from Facilities' Strategic Leadership Team (SLT)
- Continue to write/edit sections of the report to address the report's
defects.
Issues
- Nothing new this fortnight. Meetings have become the project ;(.
Key learnings
- Properly facilitated, any group can be helpful in brainstorming ways to
proceed after you've overcome the shock of bad news.
Team dynamics
- Planning team is holding together, in spite of the confusion induced by
the budget letter.
Additional comments
- Nothing.