EHSS Project Update - Jan 31, 2001

daemon@ATHENA.MIT.EDU (Rob Smyser)
Tue Jan 30 18:18:01 2001

Message-Id: <200101302317.SAA26598@melbourne-city-street.MIT.EDU>
Date: Tue, 30 Jan 2001 18:16:41 -0500
To: magellan@mit.edu
From: Rob Smyser <smyser@MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"

Project Name:   EHSS - Environmental Health & Safety Management System 
Project Leader: Rob Smyser, Rocklyn Clarke
Report Date      Jan 31, 2001 
Submitted by:    Rob Smyser
URL:  http://web.mit.edu/is/discovery/ehss/ 

Accomplishments since last report: 
- held what amounts to a end-of-discovery milestone meeting.  
- defined next steps for transition to the next phase:
   - appoint Project Mgr (Bill V has action item)
   - write an RFP to the two vendors (Bill V, T Hoole)
   - follow through on discovery report.  
- held phone meeting with Anita Nolan of the research arm of Rohm & Haas, 
a major chemical producer.  R&H is retiring a mainframe-based inventory
system.  Looking at EMAX but R&H Manufacturing has just bought SAP for the
company, now their decision path is muddied as ours was.  R&H will drive
their decision path from the Researcher-Convenience point of view (favoring
EMAX), where MIT has decided to drive it from the Occupational Safety /
Regulatory Reporting point of view (favoring MIT).  We agreed to talk more
in a few months.

Goals for the coming period: 
- Finish discovery report -- Rob got the first draft off his desk at last.  
   J Curtis now has it.

Issues:  none

Key learnings: 
- see Rohm & Haas info in accomplishments aboce

Team dynamics: 
- nothing new to report     

Additional comments: 



----------------
   Rob Smyser MIT Information Systems, N42-250d
   smyser@mit.edu	617.253.1358        
   http://web.mit.edu/smyser