[384] in magellan

home help back first fref pref prev next nref lref last post

HR-Payroll report: Feb. 2, 2000

daemon@ATHENA.MIT.EDU (Greg Anderson)
Wed Feb 2 09:18:34 2000

Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"
Message-Id: <v04020a05b4bde6d052e0@[18.177.0.74]>
Date: Wed, 2 Feb 2000 09:15:05 -0500
To: magellan@mit.edu, hr-payroll@mit.edu, jlmorgan@mit.edu, pabrady@mit.edu,
        mlhoward@mit.edu, cashaw@mit.edu
From: Greg Anderson <ganderso@MIT.EDU>

Project Name:   HR-Payroll
Project Leader: Dan Fitzgerald
Report Date       Feb. 2, 2000
Submitted by:  Greg Anderson
URL:  http://web.mit.edu/is/discovery/hrpay/

Accomplishments past period:
-  Dan met with ASPCC to continue HR-Payroll discussions: key topics were:
continue to build business case, creation of consolidated
calendar/timeline, resources and budgets for implementation, and continued
discussion of the project structure for implementation.
- Met with the Administrative Advisory Council (AAC) on Jan. 27 for an
update on the project
- Continued to meet with the Asst. Deans & School AO's for updates
- Agreed on structure of final report
- Made assignments for final report
- Esther began to put together draft of report
- Held last scheduled meeting of team on Thurs. Jan. 27, 2000
- Dan began working with SAP-Plan and SAP-IT to insure integration of
HR-Payroll project into overall scope of SAP activities.

Goals for the coming period:

-  Complete final report: team review on Feb. 8.
-  Discuss final report with sponsors (to be scheduled)
-  Meet with Doreen Morris and Asst. Deans on Feb. 9
-  Follow-up on AAC interest in working on the risk analysis
-  Continue to work on a consolidated calendar for SAP HR-Payroll with FSS.
-  Continue to work with sponsors and others to estimate resources and
project structure
-  Meet with Bob McKersie and Ed Schein on change management
-  Prepare for next meeting with ASPCC on Feb. 16.

Issues:
- Bringing together the report from a wealth of information requires a
careful balance of concision and detail.

Key learnings
- Collectively, the team will own the content and spirit of the report.
- Customers, as represented by the AAC, are ready to work on business
policies and practices; they agree that addressing these business
activities up front and early in the project is a key opportunity to
question and improve work processes
- ASPCC involvement and interest is very productive and provides a broader
set of perspectives to combine with the work of the team.
- Keeping all of the components of the work in synch is intensive.

Team dynamics:
- The team is ready to complete its work and begin the implementation efforts.

Additional comments:
-  None



home help back first fref pref prev next nref lref last post