7/30 Enterprise Printing Project Status Report

daemon@ATHENA.MIT.EDU (David F. Lambert)
Fri Jul 30 08:18:38 1999

Message-Id: <9907301218.AA29644@MIT.EDU>
Date:         Fri, 30 Jul 99 08:17:24 EDT
From: "David F. Lambert" <LAMBERT@mitvma.mit.edu>
To: Greg Anderson <ganderso@MIT.EDU>, "Theresa M. Regan" <tregan@MIT.EDU>,
        Roger Roach <rar@MIT.EDU>, Paul Page <ppage@MIT.EDU>, magellan@MIT.EDU
Cc: Enterprise Printing Discovery Project Team <discoprt@mitvma.mit.edu>


Project Name:      Enterprise Printing
Project Leader:    Dave Lambert
Report Date:       07/30/1999
Project Notebook:  http://web.mit.edu/is/discovery/enter-print/

Accomplishments for the past period:
- received the HP 8100DN pilot PostScript printer; set it up;
  requested it be added to SAP & APS; requested an IP address
- completed a third draft of the Business Analysis Report
- worked with CAO to identify additional production reports and
  associated volumes for the PostScript pilot
- scheduled meeting with Roach, Regan & Ferrara for 8/10 to discuss
  discovey to delivery transition - resources, timing and priorities

Goals for the coming period:
- print first CAO production reports on the new PostScript printer
- hold discovery to delivery transition meeting; hopefully secure
  a firm calendar commitment (see issues section below)
- make adjustments to the distributed printing recommendations based
  on check-out feedback from Support & R3-Admin
- schedule ITLT check-out
- produce second draft of RFS

Issues:
 Issues continue to be raised regarding the timing of the delivery
 effort.  This is troubling given the prior commitments to move forward.

Key learnings:
 none

Team dynamics:
 Just peachy.

Additional comments:
 none