[N.B. For members of the HR-Payroll team; Discovery teams use the format
below to give brief status reports on a bi-weekly basis. The intent is to
provide a reporting mechanism for projects without a lot of administrative
overhead. These are shared with other Discovery Project Team Leaders. If
you are interested the archive for these reports, see:
http://www.mit.edu:8008/menelaus/magellan/ . For the HR-Payroll project,
I'll be responsible for these reports]
Greg
---------------------
Project Name: HR-Payroll
Project Leaders: Dan Fitzgerald, Greg Anderson
Report Date July 28, 1999
Submitted by: Greg Anderson
URL: [to be established for the project notebook]
Accomplishments past period:
- Created draft project charter document
- Recruited and named team
- Held first team meeting, 7/22/1999
- Established rough work structure and activities
- Attended SAP Position Management demo
- Continued team recruitment effort (to replace Implementation Resource
Team representative
Goals for the coming period
- Continue team start up activities
- Begin information gathering, requirements work
- Establish meeting with sponsors
- Begin to schedule demos and site visits
Issues:
- A lot of work in a short amount of time
- Need to insure fit between MIT strategic goals and the work of the team
- Need to insure broad participation and buy-in to the work from the
various customer groups across campus
Key learnings
- Good team, complex topic, there's a lot to learn
- The discussions are rich and critical to moving the work forward.
Team dynamics:
- Very good - solid, focused team, great knowledge base for the work.
Additional comments:
- None