3rd Barton Bi-Weekly Report

daemon@ATHENA.MIT.EDU (Carl Jones)
Wed Mar 24 15:19:24 1999

Date: Wed, 24 Mar 1999 15:16:29 -0500
To: magellan@MIT.EDU
From: Carl Jones <carlj@MIT.EDU>
Cc: efc@MIT.EDU


Project Name: 3rd Barton  (Project to find a replacement for  the  
MIT Library Management System)
Project Management Team:  Carl Jones, Joan Kolias, Nina Davis-Millis
Report Date:  Feb. 24, 1999
URL: http://macfadden:9500/c3/3dbarton)


Accomplishments past period:

- Functionality and Market Survey Teams continue to meet. Entering phase
  of putting findings into a format which can be shared with the Project Mgt.
  Team and rest of the staff.
- Heard back from Scott Thorne re. setting up time for a  discussion of
  library data model and need to follow up (check everyone's schedule and
  pick a date). 
- 3rd Barton Web page updated.

Goals for the coming period:
- Project Mgrs. beginning work on the Request for Solution (RFS). Deadline
  for draft is April 12.
- Report from Market Survey Team targeted for April 9.
- Functional Checklist Teams finishing up their work.
- Schedule data-model meeting with Scott Thorne.

Key Learnings:
- Recommending Project Management Team members avoid participating on
  working groups in future, as it becomes difficult to find time for both
  project management related duties and those of the various groups. 
  This happened with regard to the Market Survey Team, where we failed 
  to find enough volunteers.
- Timetable for beginning first round of vendor demos may need to 
  be advanced into May from June because of conflicts with June national
  meetings (e.g. American Library Association summer conference, etc.). 
  This requires getting the RFS to vendors sooner than originally 
  anticipated.
- It will likely be up to the Project Mgt. Team to take the Market
  Survey information and make the initial vendor pool recommendations.

Issues: 
- Market Survey Team is having to deal with some lingering issues regarding 
  'who's in/who's out, and why'. We have tried to make the criteria for 
  inclusion as clear as possible, but there have been occasional questions
  as to how thorough the search has been.

Comments: 
- Pushing the timetable forward for vendor demos to begin may work, but 
  scheduling will be tight. We'll have to maintain some flexibility.