Project Name: IS Operational Plan Alive!
Project Leaders: Tim McGovern
Report Date: February 3, 2000
Project Notebook: http://web.mit.edu/is/discovery/iswork/
Goals listed in last report
- Schedule follow-up data modeling session to complete remaining pieces
of model.
- Prepare for Discovery wrapup, and ITLT checkout session.
Accomplishments past period
- Completed second-round of data modeling session, and identified remaining
issues, which Data Administrator and I will handle
- Completed architecture diagram, and passed on to ITIT for review. No need
for an ITIT review.
- ITLT checkout session reschedule to Feb. 10.
- Requested ITLT checkout session.
Goals for the coming period (or so)
- Continue modeling efforts, and documenting same.
- Finalize documentation of business processes.
- Document effort estimates for delivery work.
- Prepare for ITLT checkout session.
Issues
- None
Key learnings
- None
Team dynamics
- None
Additional comments
- None