[21] in iswork
Request for server for IS Operational Plan Alive!
daemon@ATHENA.MIT.EDU (Tim McGovern)
Thu Mar 23 15:50:54 2000
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"
Message-Id: <v04020a00b500315ab4c3@[18.152.1.21]>
Date: Thu, 23 Mar 2000 15:50:34 -0500
To: kelley@MIT.EDU
From: Tim McGovern <tjm@MIT.EDU>
Cc: rar@MIT.EDU, iswork@MIT.EDU
Peter,
This is a request for server hardware for the project named above.
You probably saw my mail of Feb 17 to infosys (included below), summarizing
the fact that ITLT approved the Delivery work recommendations for making
the IS Operational Plan Alive.
As part of that effort, we will be needing a server that will support the
web server, java servlets, and Oracle backend database to achieve our
goals. From conversations with Miki, we think that the overall power and
capacity requirements are consistent with what we're using for the Project
Database today -- SPARC Enterprise 250, I think.
This project is sponsored by Jim Bruce, who has asked us to be in
production by the end of June of this year, as we head into the new fiscal
year. Therefore, we need to get hardware up and running pretty quickly.
Can you please let us know when your group could provide us with the
hardware. Miki will be glad to install the web server and database
components, if your folks can get the hardware, os and kerberos support
installed.
I look forward to hearing from you...
Tim
-----
>Date: Thu, 17 Feb 2000 14:56:24 -0500
>To: infosys@MIT.EDU
>From: Tim McGovern <tjm@MIT.EDU>
>Subject: Project Update: IS Operational Plan Alive! Moves from Discovery
>to Delivery
>Cc:
>Bcc: tjm@MIT.EDU
>X-Attachments:
>
>To: All Information Systems Staff
>
>Good afternoon, everyone,
>
>On behalf of Greg Anderson and Bob Ferrara, I am very pleased to announce
>the transition of the IS Operational Plan Alive! work from I/T Discovery
>to I/T Delivery. This project has been underway since November, 1999, and
>its recommendations were accepted by ITLT last week.
>
> Notebook: http://mit.edu/is/discovery/iswork/
> Final report: (http://mit.edu/is/discovery/iswork/report.html)
>
>This project was asked to explore what would be required to keep the IS
>Operational Plan Alive. The results of that inquiry are that there are
>two different, but connected, parts to the answer: 1) evolve existing
>behavior at many levels of the organization vis-a-vis the communication of
>information about the work we're doing, and 2) develop a tool, a simple
>but extensible design, that can manage information about IS work, and
>provide staff with an easy way to review, comment, extend and apply that
>information.
>
>As this work moves into I/T Delivery, we want to create a team that will
>accomplish both aspects of the work outlined above. We are looking for
>folks from around IS who have a strong interest in participating in this
>exciting effort, and who have one or more of these skills:
>
> Organizational behavior, diagnosis, evolution and development
> Web-based application user interface design
> Web service, Oracle rdbms and UNIX system setup & administration
> Java servlet application design and development
> Web-based help and documentation design and development
> Data migration
>
>The time commitments needed are relatively small, but to be of maximal
>effect, we'd like to identify the whole team before we begin planning the
>work. Our working target for completion of the work is June of this year.
>If you have an interest in this work, and would be available during the
>timeframe above, please drop a message to <tjm@mit.edu>.
>
>The Executive Sponsor for this work is Jim Bruce, with tactical direction
>provided by Bob Ferrara and Bill Hogue. ITLT will be the final gate on
>the transition of the work into Service and Support.
>
>The team's success criterion will be to dovetail the adjustments to the
>organizational issues identified and the development of a tool to support
>those adjustments. As the team's work unfolds, we ask for your
>cooperation, input, and assistance.
>