[986] in I/T Delivery

home help back first fref pref prev next nref lref last post

HR-Payroll - end of Dec report

daemon@ATHENA.MIT.EDU (Dan Fitzgerald)
Fri Jan 3 09:00:37 2003

Message-Id: <5.0.2.1.2.20030103083007.00ab6ec0@hesiod>
Date: Fri, 03 Jan 2003 09:00:33 -0500
To: delivery@mit.edu
From: Dan Fitzgerald <danfitz@MIT.EDU>
Mime-Version: 1.0
Content-Type: multipart/alternative;
	boundary="=====================_1220756344==_.ALT"

--=====================_1220756344==_.ALT
Content-Type: text/plain; charset="us-ascii"; format=flowed

Project Name: HR-Payroll Project
Project Leader: Dan Fitzgerald
Report Date: Jan 3, 2003
URL: http://web.mit.edu/is/delivery/hrpayroll/

Accomplishments in Dec
- Proposed timeline for go-live of HR was set. It is May for Lincoln Lab 
and August for campus.
- Successful Benefits open enrollment window 2 and also successful 
transmissions of Benefit elections from open enrollment
- Tuition Assistance integration testing and subsequent transports to 
production.

Goals for Jan
- Lincoln-campus data exchange scope defined. (carry-over)
- Define joint, campus and Lincoln, reporting requirements down to the 
field level

Next Community Milestone
- Tuition Assistance ESS in Feb/March
- Tuition Assistance policy change regarding removing 6 month waiting 
period for eligibility and increasing the prepayment amount for a 1st 
course, both effective in Jan 2003.
- Data validation of Cyborg data by DLC's starting in March.

Issues
- Determination of Lincoln Lab - campus integration. Impacts scope, 
timeline, project structure, HR structure and project resources.
- Pension Payroll and HR go-lives in 2003 will impact our SAP environment 
in terms of pre-production environments, size of SAP instances, management 
of support packs, and other areas. Important that we get ahead of this change.
- Scheduling a campus integration test along with supporting the project 
testing prior to HR go-live.

--=====================_1220756344==_.ALT
Content-Type: text/html; charset="us-ascii"

<html>
Project Name: HR-Payroll Project<br>
Project Leader: Dan Fitzgerald<br>
Report Date: Jan 3, 2003<br>
URL:
<a href="http://web.mit.edu/is/delivery/hrpayroll/" eudora="autourl"><font color="#0000FF"><u>http://web.mit.edu/is/delivery/hrpayroll/</a><br>
<br>
</font>Accomplishments in Dec<br>
</u>- Proposed timeline for go-live of HR was set. It is May for Lincoln
Lab and August for campus.<br>
- Successful Benefits open enrollment window 2 and also successful
transmissions of Benefit elections from open enrollment<br>
- Tuition Assistance integration testing and subsequent transports to
production.<br>
<br>
<u>Goals for Jan<br>
</u>- Lincoln-campus data exchange scope defined. (carry-over)<br>
- Define joint, campus and Lincoln, reporting requirements down to the
field level<br>
<br>
<u>Next Community Milestone<br>
</u>- Tuition Assistance ESS in Feb/March<br>
- Tuition Assistance policy change regarding removing 6 month waiting
period for eligibility and increasing the prepayment amount for a 1st
course, both effective in Jan 2003.<br>
- Data validation of Cyborg data by DLC's starting in March.<br>
<br>
<u>Issues <br>
</u>- Determination of Lincoln Lab - campus integration. Impacts scope,
timeline, project structure, HR structure and project resources. <br>
- Pension Payroll and HR go-lives in 2003 will impact our SAP environment
in terms of pre-production environments, size of SAP instances,
management of support packs, and other areas. Important that we get ahead
of this change.<br>
- Scheduling a campus integration test along with supporting the project
testing prior to HR go-live.<br>