[924] in I/T Delivery

home help back first fref pref prev next nref lref last post

October report

daemon@ATHENA.MIT.EDU (Esther Yanow)
Wed Nov 6 10:38:21 2002

Mime-Version: 1.0
Message-Id: <p05010404b9edf96edd8f@[18.152.0.226]>
Date: Wed, 6 Nov 2002 10:38:15 -0500
To: delivery@mit.edu
From: Esther Yanow <eyanow@MIT.EDU>
Content-Type: multipart/alternative; boundary="============_-1175525398==_ma============"

--============_-1175525398==_ma============
Content-Type: text/plain; charset="us-ascii" ; format="flowed"


Project Name: Parking Project
Project Leader: Esther Yanow
Report Date: November 6, 2002 (for October)
URL:  http://web.mit.edu/is/delivery/parking-web

Accomplishments in October

* Completed the Analysis phase to ensure we have all the information we need.
* Began the Design phase.
* Ordered the servers.
* Wrote a first draft of the Support/Rollout Plan.
* Team visited the Parking Office to see how it maintains its files 
and review some of the business procedures.


Goals for November

* Continue the work in the Design phase.
* Present the first draft of the Support/Rollout Plan to the team.
* Start working on a Test Plan.


Next Community Milestone

Rollout to the community is expected to be in July 2003.   Usability 
activities, testing, and Parking Coordinators focus groups will be 
involved before then.



Issues

None

--============_-1175525398==_ma============
Content-Type: text/html; charset="us-ascii"

<!doctype html public "-//W3C//DTD W3 HTML//EN">
<html><head><style type="text/css"><!--
blockquote, dl, ul, ol, li { margin-top: 0 ; margin-bottom: 0 }
 --></style><title>October report</title></head><body>
<div><br></div>
<div>Project Name: Parking Project</div>
<div>Project Leader: Esther Yanow</div>
<div>Report Date: November 6, 2002 (for October)</div>
<div>URL:&nbsp; http://web.mit.edu/is/delivery/parking-web</div>
<div><br></div>
<div><u>Accomplishments in October</u></div>
<div><br></div>
<div>* Completed the Analysis phase to ensure we have all the
information we need.</div>
<div>* Began the Design phase.</div>
<div>* Ordered the servers.</div>
<div>* Wrote a first draft of the Support/Rollout Plan.</div>
<div>* Team visited the Parking Office to see how it maintains its
files and review some of the business procedures.</div>
<div><br></div>
<div><br></div>
<div><u>Goals for November</u></div>
<div><br></div>
<div>* Continue the work in the Design phase.</div>
<div>* Present the first draft of the Support/Rollout Plan to the
team.</div>
<div>* Start working on a Test Plan.</div>
<div><br></div>
<div><br></div>
<div><u>Next Community Milestone</u></div>
<div><br></div>
<div>Rollout to the community is expected to be in July 2003.&nbsp;&nbsp;
Usability activities, testing, and Parking Coordinators focus groups
will be involved before then.</div>
<div><br></div>
<div><br></div>
<div><u><br></u></div>
<div><u>Issues</u></div>
<div><br></div>
<div>None</div>
<div><u><br></u></div>