Events Calendar - October 2002 FINAL Status Report

daemon@ATHENA.MIT.EDU (Stephen Turner)
Fri Nov 1 12:01:58 2002

Message-Id: <5.1.0.14.2.20021101115232.014e9248@po14.mit.edu>
Date: Fri, 01 Nov 2002 12:01:54 -0500
To: delivery@mit.edu
From: Stephen Turner <sturner@MIT.EDU>
Cc: events-team@mit.edu, events-admin@mit.edu, kaw@mit.edu
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"; format=flowed

Project Name: MIT Events Calendar
Project Leader: Stephen Turner
Report Date: November 1, 2002
Submitted by: Stephen Turner
URL: http://web.mit.edu/is/delivery/eventscalendar/

Accomplishments for October 2002:

- Completed the transition of the Events Calendar from Delivery to EAST
    on October 31. This marks the end of the Events Calendar delivery
    project.
- Introduced calendar administrators to EAST.
- Paul Heffernan remains in touch with the two student authors of the Tech
   Calendar code regarding the sharing of the code with other institutions. An
   agreement is almost ready.
- Presented a hands-on custom calendar session at the IT Partners
   Conference (10/24).

Plans for next month:

- N/A

Community Milestones

- The Events Calendar Delivery project is now complete and the calendar is in
    the capable hands of EAST.

Issues:

- Thank you to all who worked on the Events Calendar delivery project in the
    last three years and to those who sent suggestions and comments.