Project Name: PDA Support
Project Leader: Rich Garcia
Report Date: May 30, 2003
Submitted by: Rich Garcia

URL: http://web.mit.edu/is/delivery/pda-support

*Accomplishments (What did we accomplish in the last period?
- Formed team
- Created notebook
- Outlined work to be performed
- Ordered and received PDAs for testing
- Obtained source code for PDA version of Webmail
- Wrote description of PDA support for IS Services web page

*Goals (What are we planning to accomplish in the next period?)
- Meet with testers to outline test procedures
- Begin testing: obtaining wireless connections, using certificates
- Get Webmail beta available for testing
- Gather information from testers for documentation

*What is the next community milestone?

*Have there been any developments that may impact the scope or schedule?
- Delays in receiving PDAs, but should not impact goal of support by Sept.

*Do we need any additional information from the client, stakeholders, sponsor?

*Issues/Key learnings

*Team Dynamics
- 