Project Name: Enterprise Backup System
Project Leader: Sebastien Sabre
Report Date: 4/18/03
URL: http://windsurf.mit.edu/ebs
Accomplishments Past Period:
----------------------------
* Continued daily maintenance and operation of NetBackup on the E40 systems.
* E40 backups success was 91% for March
* W91 implementation
- Completed installation of Netbackup Master and Media Servers
- Started testing of the W91 installation
Goals for the Coming Periods:
-----------------------------
* W91 implementation
- Complete W91 testing plan
- Define Backup Classes, Schedules, Policy for the W91 Server
- Run first full Backups
* Get final buy-in from key stake holders (ASST, R3-Admin, DOST) on the E40
implementation.
- Schedule meeting with DOST
- Schedule meeting with r3-admin
* Update project documentation and web pages.