[899] in Athena User Interface
AUI delivery report, January 2002
daemon@ATHENA.MIT.EDU (andrew m. boardman)
Tue Feb 12 23:51:23 2002
Date: Tue, 12 Feb 2002 23:51:20 -0500
Message-Id: <200202130451.XAA02273@pothole.mit.edu>
From: "andrew m. boardman" <amb@MIT.EDU>
To: delivery@mit.edu
CC: aui@mit.edu
[If you've seen this already, it hasn't changed, but it didn't make it
all of the way out the first time around...]
Project Name: Athena User Interface Project
Project Leader: Andrew Boardman
Report Date: 8 February 2002
Project URL: http://web.mit.edu/aui/notebook/
Accomplishments Past Period:
- Started a new round of comparative usability testing.
Goals for Next Period:
- Find more test subjects so as to finish follow-on usability testing.
- Finalize documentation based on the above.
Notes:
- Finding subjects for usability tests has been hard. (If you're reading
this and have potential testers, drop me a note. We offer small bribes.)
Team Dynamics:
- Fine.