[17832] in athena10

home help back first fref pref prev next nref lref last post

Current status of NEUTRON-STAR, PACKAGE-FUSION, and HECATONCHEIRES in

daemon@ATHENA.MIT.EDU (Cel Skeggs)
Fri Nov 19 18:03:09 2021

From: Cel Skeggs <cela@mit.edu>
To: <debathena@mit.edu>
CC: <sipb-hwops@mit.edu>
Message-ID: <8cdd4c55-a509-a021-5379-911ba67f5b25@mit.edu>
Date: Fri, 19 Nov 2021 18:02:56 -0500
MIME-Version: 1.0
Content-Type: text/plain; charset=utf-8; format=flowed
Content-Transfer-Encoding: 7bit
Content-Language: en-US

Hi Debathena maintainers,

SIPB Hardware Operations (HWOPS) is surveying the current machines in 
the SMR, to determine which servers need to be on UPS power, which 
servers don't need UPS power, and which servers can be completely 
decommissioned and removed from the rack.

As far as we can tell, NEUTRON-STAR, PACKAGE-FUSION, and HECATONCHEIRES 
appear to be the current Debathena machines in the SMR. Our current 
understanding is that these machines are not used for online production 
services, but rather used for building packages for Debathena, and 
therefore would be able to be shut off during a power outage without 
causing any serious problems. Correspondingly, we believe that they do 
not require UPS power. Could you let us know whether this seems correct? 
If this were the case, it would help us limit our power consumption and 
reduce the budgetary impact of buying new UPSes.