Notes from 11/04 meeting (Barbara, Debi, Wade)

-  Updated project plan (see below).  Specifically, new items added to the
   Scopus GUI, web/oracle and email/oracle applications.

-  Barbara to conduct QA on the ragone/ho Scopus GUI changes.

-  Four page Quick Guide written, should install on project notebook page.

-  Student training scheduled for 11/4

-  Decided to feed the computing-help@mit.edu and sap-help@mit.edu mailing
   lists to Oracle, without customer acknowledgements as a test of this
   function.  Looking for target date of 11/7.

-  Debi will complete the password change for existing accounts by
   11/7.  Filemaker conversion looks good, minor changes needed.

-  Peter/David to complete the Scopus GUI changes

---------------------------------------------------------------------

Project dates and milestones:

-  Dates:  Still looking for final date for Scopus development is end of day
   Monday November 10, 1997.

-  Cut-over from Filemaker to Oracle to begin after 5:00 pm on
   Friday, November 14, 1997.  Probably completed over the weekend and
   production available on Monday morning November 17, 1997.

-  Web/Oracle application is in good shape.  May be some missing fields
   that need to be added.  Development priority will shift to completing
   the email/oracle application with possible "live" testing before the
   November rollout date.  The web/oracle application will continue to
   proceed after the Scopus rollout.

---------------------------------------------------------------------

The critical path items to manage are:

-  Set final date for development changes (NOTE: timeline leaves little time
   for development, therefore, need to identify showstoppers versus items
   that can be changed for a future release)

-  Testing, testing, testing:  Specifically the Scopus GUI and with
   regards to the Filemaker legacy data import.  Goal is to ensure
   continuity of business.

-  Identification of resources to ensure transition to Service and
   committment of Delivery resources to ensure a phase 2 release.

---------------------------------------------------------------------

HELP TOOLS RELEASE 1.1 WORKPLAN

TOOLS

Web/Oracle

      Complete application as follows:

      Initial priority is:
      -  Need further check on consulting access, don't allow legacy people to
         gain access (as currently is the case).  New view should resolve.
      -  "Find Open" query should be consistent with Scopus, regarding
         display of frozen status and taken field.
      -  Add search by category

      Rest of proposed changes:
      -  "modified by" username needs to be filled in via the web
      -  Change search "within 60 days" to between "30 and 60". ??
      -  Add "MIT Computing Help Desk" with appropriate mail address to the
         consultant reply to customer mail function.
      -  Change result screen working "Only first 100 records will be shown".
         to "Showing first xx matching entries".
      -  Main screen:  Change "Client:" to "Client Last Name:".
      -  Sorting on log status, sort in descending order by MIT_WEIGHT
      -  Change default sort order by (descending) log status weight and
         then log number on the "Staff" side?
      -  Revise format of the email sent to the customer.
      -  Change "Notify customer via email" to "Send customer new entry via
         email" or "Send customer new case history" depending what happens.
      -  Make this checkbox only appear if we know the customer's email
         address?
      -  Search on other stati, including "taker" field
      -  Add hostname, machine location, vendor and account number to
         the IP address request on the submit screen.
      -  Add 10 additional network fields to the log screen (see mail)
      -  Add 3 fields (taker, thaw, freeze) only for the consultant
      -  Make category, and status field - bold, red
      -  Put "client" in both received by and modified by fields when
         customer submits log
      -  Duplicate IP address in the network section
      -  Move network fields infront of the log history text
      -  When customer appends to an existing log, change status to unseen
      -  Add word "client", in addition to existing client name.

Scopus GUI:

      Complete GUI changes as follows (priority is shown):
      1. Add new Find Open scripts per category (see debi's mail)
      2. Add hostname field (needs to be added to database) to
         the network screen.
      3. Remove clipboard button from the logs screen.
      4. When creating a new record, fill in modified by user and
         timestamp with same information that is used for creation date.
      5. Change display for taken field to use a view (needs to be
         created) that does not show legacy users.
      6. Repeat the IP Address field as a read-only field on the
         network screen.

      Completed items 10/31
      1. Add Next Step field
      2. Modify Find Open script to handle frozen date (do not show
         Frozen logs in result window with a date greater than today.
      3. Bug fix: on required field error, status reverts to New
      4. Bug check: switching between main log and network screen, old
         data shows on network screen when selecting new main log.
      5. Change label from "Thaw" to "Close on Thaw"

      Status:     Working
      Assigned:   Ho/Ragone
      Target:     11/10

Email/Oracle

   -  Need acknowldegement message on "reply logid"
   -  Appending to existing log, change status to "unseen"
   -  Review customized acknowldegement message on new message
   -  Populate received by and modified fields with "client"
   -  history_search_field needs to be populated
   -  Needs testing, begin to use computing-help, sap-help lists
   -  Change history to not have fixed upper limit
   -  Add code to handle bounced mail

   Completed 10/31
   -  Review, complete and migrate to production:
   -  Minor changes include not hardcoding the login password
      acknowledgement message.
   -  Install on production machine, revise syslog

      Status:     Open
      Assigned:   Wade
      Target:     11/07

SYSTEM:

Database

      Add missing database fields:
	Next Step field.  (completed 10/21)
        hostname fiel to mit_ni table
      Status:     Completed
      Assigned:   Wade
      Target:     11/07

      Create cron process to modify Frozen logs based on Frozen date
        and status of Thaw code, as well as set the close date, otherwise
        set status to pending on thaw date.
      Status:     Open
      Assigned:   Wade
      Target:     11/14

      Create new view "legacy_users" to not display legacy users.
      Status:     Open
      Assigned:   Wade
      Target:     11/14

      Export test help-them database to production help-it database
      Status:     First attempt completed
      Assigned:   Wade
      Target:     10/22

Data updates:

      Update lookup/code tables as follows:
        Add "Web" to Method, add "Unseen" to Status,
        remove "Referred" from status, add "Projects" and "CWIS"
        to Category, remove "Waiting" from status.

	Status:   Completed 10/20

Account table maintenance:

      Review, modify and create new accounts:
        Add "client" to profile and users table.
        Drop those accounts where people do not need to login.
        Move old consultants to status of Legacy
        Add new users
        Add Legacy users

      Status:     Completed 10/20

      Alter the password for existing accounts
      Status:     Open
      Assigned:   Debi
      Target:     10/27

Overall testing:

      Perform business, stress and data testing
      Status:     Open
      Assigned:   Computing Help Desk
      Target:     10/22

ROLLOUT:

Filemaker/Oracle Conversion:

      Complete first pass and load of data

      Status:     Completed 10/21

      Complete second pass and load of data
      Need upper case for complete second pass and load of data

      Status:     Open
      Assigned:   Debi/Wade
      Target:     10/30

      Complete FINAL load of data

      Status:     Open
      Assigned:   Debi/Wade
      Target:     11/14

Scopus deployment:

      Install Scopus NT on machines as needed:
        Need to deploy installer on net-dist.
      Status:     Open
      Assigned:   Smyser/Ho
      Target:     10/22

Scopus Training:

      Ensure consultants are ready
      Status:     Open
      Assigned:   Allen/Smyser/Ragone/Fuchs
      Target:     Two training sessions planned, 10/31

Solicit appropriate feedback

      Check with DCS/Sampson for issues
      Status:     Open
      Assigned:   Fuchs/Goguen
      Target:     10/17

---------------------------------------------------------------------
HELP TOOLS RELEASE 1.2 ??

Solaris Scopus GUI needs to work with ANO
Web/Oracle - send consultant mail when customer updates log
Add private comments field
Review design to look at records that exceed limit on result query
Add mail CC: field when consultant sends mail to customer (web/oracle)
Evalute issue with multpile saves in Scopus by same user on diff. machines
IP address should perform a "hostinfo" to check for existance