Updated release 1.0 schedule

daemon@ATHENA.MIT.EDU (Steven Wade Neiterman)
Thu Oct 10 17:29:55 1996

Date: Thu, 10 Oct 1996 17:29:48 +0100
To: tooltime@MIT.EDU
From: Steven Wade Neiterman <wade@MIT.EDU>
Cc: helpstaff@MIT.EDU

Based on today's Help Desk staff meeting, here is an updated schedule.  The
major changes include:

-  Delayed Tue Oct 15 "statement of record" release date

-  Wed Oct 16 - Release 1.0 completed, acceptance testing completed, results
                sent to Bill Hogue with recommendation.  Acceptance testing
                is designed to identify critical issues (e.g. show stoppers)
                that would preclude consultants from doing work as outlined
                in the release 1.0 functional specification.

-  Thu Oct 17 - Help Desk staff review recommendation

-  Fri Oct 18 - 5:00 pm - Possible date for release 1.0 rollout

------------------------------------------------------------------------
Last updated October 10, 1996

------------------------------------------------------------------------
Mon Sep 23

Tue Sep 24 10:00 tooltime meeting

Wed Sep 25  2:00 implementation meeting

Thu Sep 26 Rob/Esther begin work on final draft training document
           Tom/Lynne begin Scopus review/technology transfer
           Complete testing against production database

Fri Sep 27 Complete release 1.0b6

------------------------------------------------------------------------

Mon Sep 30 Tooltime team begin review of 1.0b6

Tue Oct  1 10:00 tooltime meeting

Wed Oct  2 2:00 implementation meeting
           Complete 1.0b6 testing

Thu Oct  3 Begin 1.0b7 changes

Fri Oct  4 Complete training document
           Complete review of production environment, including a test
           of development tools

------------------------------------------------------------------------

Mon Oct  7 Migrate test environment to production for training

Tue Oct  8 10:00 tooltime meeting, prioritize final release changes

Wed Oct  9  2:00 implementation meeting - cleanup Filemaker data, test 1.0b7

Thu Oct 10 Help Desk Staff training 16-720 10:00 am (incl. DCS)
           Migrate test database to production (database services)

Fri Oct 11 Generate 60 copies of training document
           Complete release 1.0b7, including testing of changes
           Complete load of 5,000 records for performance testing
           Ensure software deployed and accounts generated

------------------------------------------------------------------------

Mon Oct 14 Holiday

Tue Oct 15 Student Holiday
           Application code release 1.0 completed
           12:00 - 2:00 Help Desk staff completes "self" learning of system
            5:00 - 6:00 PM Student training

Wed Oct 16 10:00 - 12:00 PM, Staff acceptance testing
            3:00 -  5:00 PM, Student "self" learning & acceptance test
            Release 1.0 concluded with acceptance test document

Thu Oct 17  Help Desk Staff agree on rollout date (based on acceptance
            testing, sufficient training, deployment and general readyness
            to begin using Scopus)

            Continue with release 1.0 support activities, including
            deployment and testing of password changing program, final
            check of production database (migrate test to production),
            test database management issues (e.g. install SNS), etc.

Fri Oct 18  Migrate Filemaker data to production 5:00 pm ?????