Based on today's Help Desk staff meeting, here is an updated schedule. The
major changes include:
- Delayed Tue Oct 15 "statement of record" release date
- Wed Oct 16 - Release 1.0 completed, acceptance testing completed, results
sent to Bill Hogue with recommendation. Acceptance testing
is designed to identify critical issues (e.g. show stoppers)
that would preclude consultants from doing work as outlined
in the release 1.0 functional specification.
- Thu Oct 17 - Help Desk staff review recommendation
- Fri Oct 18 - 5:00 pm - Possible date for release 1.0 rollout
------------------------------------------------------------------------
Last updated October 10, 1996
------------------------------------------------------------------------
Mon Sep 23
Tue Sep 24 10:00 tooltime meeting
Wed Sep 25 2:00 implementation meeting
Thu Sep 26 Rob/Esther begin work on final draft training document
Tom/Lynne begin Scopus review/technology transfer
Complete testing against production database
Fri Sep 27 Complete release 1.0b6
------------------------------------------------------------------------
Mon Sep 30 Tooltime team begin review of 1.0b6
Tue Oct 1 10:00 tooltime meeting
Wed Oct 2 2:00 implementation meeting
Complete 1.0b6 testing
Thu Oct 3 Begin 1.0b7 changes
Fri Oct 4 Complete training document
Complete review of production environment, including a test
of development tools
------------------------------------------------------------------------
Mon Oct 7 Migrate test environment to production for training
Tue Oct 8 10:00 tooltime meeting, prioritize final release changes
Wed Oct 9 2:00 implementation meeting - cleanup Filemaker data, test 1.0b7
Thu Oct 10 Help Desk Staff training 16-720 10:00 am (incl. DCS)
Migrate test database to production (database services)
Fri Oct 11 Generate 60 copies of training document
Complete release 1.0b7, including testing of changes
Complete load of 5,000 records for performance testing
Ensure software deployed and accounts generated
------------------------------------------------------------------------
Mon Oct 14 Holiday
Tue Oct 15 Student Holiday
Application code release 1.0 completed
12:00 - 2:00 Help Desk staff completes "self" learning of system
5:00 - 6:00 PM Student training
Wed Oct 16 10:00 - 12:00 PM, Staff acceptance testing
3:00 - 5:00 PM, Student "self" learning & acceptance test
Release 1.0 concluded with acceptance test document
Thu Oct 17 Help Desk Staff agree on rollout date (based on acceptance
testing, sufficient training, deployment and general readyness
to begin using Scopus)
Continue with release 1.0 support activities, including
deployment and testing of password changing program, final
check of production database (migrate test to production),
test database management issues (e.g. install SNS), etc.
Fri Oct 18 Migrate Filemaker data to production 5:00 pm ?????