Scopus Implemtation Schedule

daemon@ATHENA.MIT.EDU (Steven Wade Neiterman)
Mon Sep 30 10:37:18 1996

Date: Mon, 30 Sep 1996 10:38:19 +0100
To: tooltime@MIT.EDU
From: Steven Wade Neiterman <wade@MIT.EDU>

First draft - schedule for review at tooltime meeting 9/30.

------------------------------------------------------------------------
Mon Sep 23

Tue Sep 24  10:00 tooltime meeting

Wed Sep 25  2:00 implementation meeting

Thu Sep 26  Rob/Esther begin work on final draft training document
            Tom/Lynne begin Scopus review/technology transfer
            Complete testing against production database

Fri Sep 27  Complete release 1.0b6

------------------------------------------------------------------------

Mon Sep 30  Tooltime team begin review of 1.0b6

Tue Oct  1  10:00 tooltime meeting

Wed Oct  2   2:00 implementation meeting

Thu Oct  3

Fri Oct  4  Complete training document
            Complete 1.0
            Complete review of production environment, including a test
              of development tools

------------------------------------------------------------------------

Mon Oct  7

Tue Oct  8  Help Desk Student training 5:00 pm, hand out training doc
            10:00 tooltime meeting

Wed Oct  9  2:00 implementation meeting - cleanup Filemaker data
            Ensure accounts established, software distributed
            Include password changing program, correct tnsnames.ora

Thu Oct 10  Help Desk Staff training 16-720 10:00 am (incl. DCS?)
            Migrate test database to production (database services)

Fri Oct 11  Migrate Filemaker data to production 5:00 pm?

------------------------------------------------------------------------

Mon Oct 14  Holiday

Tue Oct 15  Student Holiday
            ** Help Desk now using Scopus instead of Filemaker **

Wed Oct 16

Thu Oct 17

Fri Oct 18