First draft - schedule for review at tooltime meeting 9/30.
------------------------------------------------------------------------
Mon Sep 23
Tue Sep 24 10:00 tooltime meeting
Wed Sep 25 2:00 implementation meeting
Thu Sep 26 Rob/Esther begin work on final draft training document
Tom/Lynne begin Scopus review/technology transfer
Complete testing against production database
Fri Sep 27 Complete release 1.0b6
------------------------------------------------------------------------
Mon Sep 30 Tooltime team begin review of 1.0b6
Tue Oct 1 10:00 tooltime meeting
Wed Oct 2 2:00 implementation meeting
Thu Oct 3
Fri Oct 4 Complete training document
Complete 1.0
Complete review of production environment, including a test
of development tools
------------------------------------------------------------------------
Mon Oct 7
Tue Oct 8 Help Desk Student training 5:00 pm, hand out training doc
10:00 tooltime meeting
Wed Oct 9 2:00 implementation meeting - cleanup Filemaker data
Ensure accounts established, software distributed
Include password changing program, correct tnsnames.ora
Thu Oct 10 Help Desk Staff training 16-720 10:00 am (incl. DCS?)
Migrate test database to production (database services)
Fri Oct 11 Migrate Filemaker data to production 5:00 pm?
------------------------------------------------------------------------
Mon Oct 14 Holiday
Tue Oct 15 Student Holiday
** Help Desk now using Scopus instead of Filemaker **
Wed Oct 16
Thu Oct 17
Fri Oct 18