Scopus Implementation Meeting June 25, 1996

daemon@ATHENA.MIT.EDU (Steven Wade Neiterman)
Fri Jun 28 09:24:15 1996

Date: Fri, 28 Jun 1996 09:26:31 -0400
To: tooltime@MIT.EDU
From: wade@MIT.EDU (Steven Wade Neiterman)

Scopus Implementation Meeting June 25, 1996

Attending: Lane, Oh, Pakulat, Rosen, Saylor, Wade, Willis

Agenda
1. 1.0b3 Testing, Expectations and Process
2. On-going Tasks and Resources
3. Next Steps

1. 1.0b3 Testing, Expectations and Process

   - Most (95+%) of the critical and "easy fix" items identified from
     last week's testing of 1.0b2 have been completed.

   - Pre-requisite for 1.0b3 testing is the import of the Filemaker
     database into Scopus.

   - As compared to the Functional Specification, it is believed we have
     met the initial intent with the exception of the "thaw" automation.

   - Issues:
     - When to test
       - Tooltime team to test this week, hopefully by Friday,
         the Filemaker data will be available.
       - Starting next week (Tuesday, July 2), the helpstaff will test

     - How to test
       - Bryn will create a template of information to be sent to
         the Help Desk staff (helpstaff@mit.edu).

     - Feedback
       - helpstaff will be asked to send information within a day or
         two after testing (if testing goes as planned and starts on July 2,
         then feedback needs to be completed by end of day July 3).

     - Assessment will occur during next tooltime meeting, July 9.

  - John expressed a concern that the netinstall information needs to
    be reviewed further. John has taken the action item to review the
    functions  against the Functional Specification and send comments if there
    are questions, issues or other needs. The team will then need to asses
    those items.

  - Question: If this is the last beta release and thus the last chance
    to send in comments?

    Until we see the feedback on 1.0b3, we will not know if this is the last
    release. It should be close to a last release as we compare the release to
    the Functional Specification, determine it's value against the business and
    asses the operational stability of the application.

2. On-going tasks and resources:

   Eugene Zherebilov         Mapping Scopus datamodel into Silverrun
                             Created first model, identified need to
                             add relationships between entities.  Due to
                             time and resources, this may not occur until
                             after release 1.0

   Brett Rosen               Will help initially with Filemaker conversion,
                             and add his expertise of Tcl and Unix system
                             administration to help evaluate the InfoTEAM
                             product for email notification, escalation and
                             business rule implementation.  Brett will also
                             initially help with testing.

   Mary Weiss                Adding a view to the warehouse to combine
                             employee data and student data in one extract.
                             Expected completion 6/28.

   Peter Kelley              Working on ordering production machine.
                             Wade talked to Peter on Monday 6/24, waiting
                             for email.

   Ray Charbonneau           Working on 32 bit Scopus installer

   Peter Lee                 Working on Filemaker to Scopus migration,
                             need completion by 6/28.

   Lynne Sousa               Working on 1.0b3 Scopus release, testing and
                             bringing design issues to the team for review.

   Lynne Sousa               Coordinating support categories as related to
   Al Willis                 software categories.
   Kevin Cunningham

   Peter Lee                 Storybook and training needs for helpstaff

   Jeff Harrington           Working on SQL*Net installer (used by Scopus).
                             Jeff has a working prototype, shortly this will
                             be used by the Scopus network deployment.

   Lynne Sousa               Maintain commented Tcl, will evaluate using
                             RCS version control.

   Esther Yanow              Begin (7/1) helping with Scopus documentation.
                             Initially, will discuss with Lynne rules we
                             applied to the Tcl code that may not have been in
                             the Functional Specification and should be
                             documented.  Will also put the Design document
                             on the Web.  May also help write a short
                             training document.

   Steven Wade               Write System Architecture document

   Steven Wade               Pursue issues and problem resolution with
                             Scopus

   Tooltime team             Test 1.0b3, prioritize items for work.
                             Maintain list of items needing resolution.

3. Next Steps

   Meeting currently scheduled for
   July 2, 1996
   10:00 am
   11-124A

   The Help Desk is moving on July 1.  In addition, time may be needed
   for testing.  Will evaluate the need for the meeting Monday July 1 and
   send mail if the meeting is to be canceled.