Attending: Lane, Oh, Pakulat, Rosen, Saylor, Wade, Willis
Agenda
1. 1.0b3 Testing, Expectations and Process
2. On-going Tasks and Resources
3. Next Steps
1. 1.0b3 Testing, Expectations and Process
- Most (95+%) of the critical and "easy fix" items identified from
last week's testing of 1.0b2 have been completed.
- Pre-requisite for 1.0b3 testing is the import of the Filemaker
database into Scopus.
- As compared to the Functional Specification, it is believed we have
met the initial intent with the exception of the "thaw" automation.
- Issues:
- When to test
- Tooltime team to test this week, hopefully by Friday,
the Filemaker data will be available.
- Starting next week (Tuesday, July 2), the helpstaff will test
- How to test
- Bryn will create a template of information to be sent to
the Help Desk staff (helpstaff@mit.edu).
- Feedback
- helpstaff will be asked to send information within a day or
two after testing (if testing goes as planned and starts on July 2,
then feedback needs to be completed by end of day July 3).
- Assessment will occur during next tooltime meeting, July 9.
- John expressed a concern that the netinstall information needs to
be reviewed further. John has taken the action item to review the
functions against the Functional Specification and send comments if there
are questions, issues or other needs. The team will then need to asses
those items.
- Question: If this is the last beta release and thus the last chance
to send in comments?
Until we see the feedback on 1.0b3, we will not know if this is the last
release. It should be close to a last release as we compare the release to
the Functional Specification, determine it's value against the business and
asses the operational stability of the application.
2. On-going tasks and resources:
Eugene Zherebilov Mapping Scopus datamodel into Silverrun
Created first model, identified need to
add relationships between entities. Due to
time and resources, this may not occur until
after release 1.0
Brett Rosen Will help initially with Filemaker conversion,
and add his expertise of Tcl and Unix system
administration to help evaluate the InfoTEAM
product for email notification, escalation and
business rule implementation. Brett will also
initially help with testing.
Mary Weiss Adding a view to the warehouse to combine
employee data and student data in one extract.
Expected completion 6/28.
Peter Kelley Working on ordering production machine.
Wade talked to Peter on Monday 6/24, waiting
for email.
Ray Charbonneau Working on 32 bit Scopus installer
Peter Lee Working on Filemaker to Scopus migration,
need completion by 6/28.
Lynne Sousa Working on 1.0b3 Scopus release, testing and
bringing design issues to the team for review.
Lynne Sousa Coordinating support categories as related to
Al Willis software categories.
Kevin Cunningham
Peter Lee Storybook and training needs for helpstaff
Jeff Harrington Working on SQL*Net installer (used by Scopus).
Jeff has a working prototype, shortly this will
be used by the Scopus network deployment.
Lynne Sousa Maintain commented Tcl, will evaluate using
RCS version control.
Esther Yanow Begin (7/1) helping with Scopus documentation.
Initially, will discuss with Lynne rules we
applied to the Tcl code that may not have been in
the Functional Specification and should be
documented. Will also put the Design document
on the Web. May also help write a short
training document.
Steven Wade Write System Architecture document
Steven Wade Pursue issues and problem resolution with
Scopus
Tooltime team Test 1.0b3, prioritize items for work.
Maintain list of items needing resolution.
3. Next Steps
Meeting currently scheduled for
July 2, 1996
10:00 am
11-124A
The Help Desk is moving on July 1. In addition, time may be needed
for testing. Will evaluate the need for the meeting Monday July 1 and
send mail if the meeting is to be canceled.