[618] in sapr3-soft

home help back first fref pref prev next nref lref last post

Scheduling Agreements

daemon@ATHENA.MIT.EDU (Cheatham, Mike)
Thu Nov 20 08:39:27 1997

To: sapr3-soft@MIT.EDU
Date: 20 Nov 1997 07:22:28 -0600
From: "Cheatham, Mike" <Mike.Cheatham@COMPAQ.com> (by way of SAP Moderator <sap-request@realtimeusa.com>)

Has anybody used Scheduling agreements with SAP configured to create 
schedule lines automatically from MRP?  I'm trying to set-up and test 
this option and so far I have everything working except after I 
execute a Goods Receipt referencing the Scheduling Agreement SAP 
prevents me from doing any further Good Receipts to that SA.  I get a 
PU quantity exceeded error.  SAP is populating the ordered quantity 
field in the GR document with the quantity of the first Goods Receipt. 
 Any suggestions would be greatly appreciated.

Regards,

Michael Cheatham

----------------------------------------------------
comp.soft-sys.business.sap is a moderated newsgroup.
Postings are archived and available from the
Realtime USA web site at http://www.realtimeusa.com
----------------------------------------------------

home help back first fref pref prev next nref lref last post