Has anybody used Scheduling agreements with SAP configured to create
schedule lines automatically from MRP? I'm trying to set-up and test
this option and so far I have everything working except after I
execute a Goods Receipt referencing the Scheduling Agreement SAP
prevents me from doing any further Good Receipts to that SA. I get a
PU quantity exceeded error. SAP is populating the ordered quantity
field in the GR document with the quantity of the first Goods Receipt.
Any suggestions would be greatly appreciated.