[7627] in Hotline Meeting

home help back first fref pref prev next nref lref last post

1-115 flood Updated note

daemon@ATHENA.MIT.EDU (jjmorey@Athena.MIT.EDU)
Mon Feb 3 08:14:21 1992

From: jjmorey@Athena.MIT.EDU
To: hotline@Athena.MIT.EDU
Cc: rita@Athena.MIT.EDU
Date: Mon, 03 Feb 92 08:14:05 EST


Old note in resolved 13987.

A/C units in this room appear to working fine for now.
Some of the cleanup/repairs have been completed.
Bob Barlow from Phys Plant and myself will be meeting Contractor and
workers in 1-115 at 7:00am 2-5-92 to complete work.
There are no class's in the morning so this should not interupt anyone.


--jjmorey

home help back first fref pref prev next nref lref last post