[69878] in Hotline Meeting
Bldgs. W4 and W5 Critical All Steam Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 19 11:49:58 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71D55@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bailey@mit.edu'" <bailey@mit.edu>,
"'mwhelan@mit.edu'"
<mwhelan@mit.edu>,
"'general@mit.edu'" <general@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'rberlin@mit.edu'"
<rberlin@mit.edu>,
"'wganger@mit.edu'" <wganger@mit.edu>
Cc: RM-PipeSys <rm-pipesys@mit.edu>,
"'shutdown@plant.mit.edu'"
<shutdown@PLANT.MIT.EDU>
Date: Wed, 19 Nov 2003 11:49:49 -0500
> To: bailey@mit.edu; mwhelan@mit.edu; general@mit.edu; shutdowns@mit.edu;
> rberlin@mit.edu; wganger@mit.edu
> Cc: RM-PipeSys; shutdown@plant.mit.edu
> Subject: Bldgs. W4 and W5 Critical All Steam Shutdown Request
>
>
The following Critical All Steam shutdown request for Bldgs. W4 and W5 on
Friday, November 21, 2003 is for your information and comment. Would you
please let me know whether this does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Critical
> Building: W4 and W5
> Date: 11/21/2003
> Day: Friday
> Time: 9:30 AM - 5:30 PM
> System: All Steam/Hot Domestic/Heating Hot Water/Supply Heating
> Duration: 8 hours
> Reason:
> Multiple 200# steam weld leaks in Manhole 1306.
>
> Effect:
> Loss of high, medium and low pressure steam. This means that no hot
> domestic water (for showers, bathroom and kitchenk sink faucets), heating
> hot water (building heat) or supply ventilation (via ceiling supply fans)
> will be operational during the 8-hour Critical shutdown period.
>
>