Bldg 13 hot & cold lab process water, acid water and DI water shu

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Nov 14 08:41:46 2003

Message-ID: <568F0AEE7A57D511923900508B556451045A85A1@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'elk@mit.edu'" <elk@MIT.Edu>, "'generoso@mit.edu'" <generoso@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>, "'src@mit.edu'" <src@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 14 Nov 2003 08:41:38 -0500

> To: 	B-Zone; Cust-Coach; elk@mit.edu; generoso@mit.edu; schedule@mit.edu;
> src@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg 13 hot & cold lab process water, acid water and DI
> water shutdown request for 11/19
> 
> 
The following shutdown request is for building 13 in all labs on the east
end of the building on 11/19/03.  Could you please let me know if this does
or does not meet with your approval?

Thank you
Dawn Simonelli
Repair and Maintenance


> Status: Normal
> Building: 13 rooms 3136, 3124, 3135, 3123, 4136, 4124, 4139, 4148, 4147,
> 4139, 4135, 4123, 5127, 5128, 5132, 5140, 5148, 5143, 5147, 2132, 2128,
> 2144, 2148, 2147, 2143, 2135, 2123, 5119 & 5120. 
> Date: 11/19/2003
> Day: Wednesday
> Time: 6 am - 10 am
> System: Hot and cold lab processed water, acid waste and DI water.
> Duration: 4 hours
> Reason: 
> Relocate acid waste piping to make way for additional piping.  Relocate 2
> ft of DI piping. 
> 
> Effect: 
> There will be a loss of hot and cold lab processed water, de-ionized water
> and lab waste drainage at this time. 
> 
> 