[69696] in Hotline Meeting
Bldg 38 low pressure steam shutdown request for 11/18.
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Nov 13 14:28:37 2003
Message-ID: <568F0AEE7A57D511923900508B556451045A859B@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: "'agallant@mit.edu'" <agallant@mit.edu>,
"'amcgurl@rle.mit.edu'"
<amcgurl@rle.mit.edu>,
B-Zone <B-Zone@mit.edu>, Cust-Coach
<cust-coach@mit.edu>,
"'edc@mit.edu'" <edc@mit.edu>, "'pmorley@mit.edu'"
<pmorley@mit.edu>,
"'rroscoe@mit.edu'" <rroscoe@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'wrgibbs@rle.mit.edu'"
<wrgibbs@rle.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 13 Nov 2003 14:25:07 -0500
> To: agallant@mit.edu; amcgurl@rle.mit.edu; B-Zone; Cust-Coach;
> edc@mit.edu; pmorley@mit.edu; rroscoe@mit.edu; schedule@mit.edu;
> wrgibbs@rle.mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg 38 low pressure steam shutdown request for 11/18.
>
>
The following shutdown request is for building 38 on 11/18/03. Could you
please let me know if this does or does not meet with your approval?
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Normal
> Building: 38
> Date: 11/18/2003
> Day: Tuesday
> Time: 6 am - 10 am
> System: Low pressure steam, heating hot water, and supply air heating.
> Duration: 4 hours
> Reason:
> Tie in service to new air handling unit serving the first floor.
>
> Effect:
> There will be no heating hot water, supply air heating or low pressure
> steam during this time.
>
>