[69661] in Hotline Meeting
Bldg. 8 - 120/208 Volt Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 12 12:35:33 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71CDB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'carolr@mit.edu'" <carolr@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'ghughes@mit.edu'" <ghughes@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'lechtman@mit.edu'"
<lechtman@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 12 Nov 2003 12:34:15 -0500
> To: C-Zone; carolr@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; lechtman@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 8 - 120/208 Volt Power Shutdown Request
>
>
The following 120/208V building power shutdown request for Bldg. 8 - 2nd
floor only on Saturday, 11/15/03 is for your information and comment. Would
you please let me know whether this does or does not meet with your
approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 8 - 2nd floor only
> Date: 11/15/2003
> Day: Saturday
> Time: 6 AM - 2 PM
> System: Building Power - 120V, 208V normal power
> Duration: 8 hours
> Reason:
> Activate new pwoer panels for 2nd floor Van Vliet Lab renovation.
>
> Effect:
> Loss of 120V, 208V normal power in Bldg. 8 - 2nd floor. This means that
> no computers, lighting or receptacles will operational during the
> shutdown period.
>
>