Bldg. 26 - Emergency All Steam/Condensate Return Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 10 12:37:17 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D71CAF@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-PipeSys <rm-pipesys@mit.edu>,
        "'amcgurl@rle.mit.edu'"
	 <amcgurl@rle.mit.edu>,
        B-Zone <B-Zone@mit.edu>, Cust-Coach
	 <cust-coach@mit.edu>,
        "'dudley@mit.edu'" <dudley@mit.edu>,
        "'khewitt@mit.edu'" <khewitt@mit.edu>,
        "'ljtrudel@mit.edu'"
	 <ljtrudel@mit.edu>,
        "'lsc@mit.edu'" <lsc@mit.edu>, "'mhankin@mit.edu'"
	 <mhankin@mit.edu>,
        "'nsteele@mit.edu'" <nsteele@mit.edu>,
        "'safety@mit.edu'" <safety@mit.edu>,
        "'schedule@mit.edu'"
	 <schedule@mit.edu>,
        "'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        Michael Correira
	 <mmcorrei@PLANT.MIT.EDU>,
        "'dcosta@mit.edu'" <dcosta@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        Operators
	 <Operators@PLANT.MIT.EDU>
Date: Mon, 10 Nov 2003 12:37:10 -0500

> To: 	RM-PipeSys; amcgurl@rle.mit.edu; B-Zone; Cust-Coach; dudley@mit.edu;
> khewitt@mit.edu; ljtrudel@mit.edu; lsc@mit.edu; mhankin@mit.edu;
> nsteele@mit.edu; safety@mit.edu; schedule@mit.edu; wrgibbs@rle.mit.edu;
> shutdowns@mit.edu; Michael Correira; dcosta@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: 	Bldg. 26 - Emergency All Steam/Condensate Return Shutdown
> 
> 
The following emergency all steam/condenste return shutdown for Blg. 26 -
all on Monday, November 10, 2003 PM is for your information.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Emergency
> Building: 26 - All
> Date: 11/10/2003
> Day: Monday
> Time: 1 PM - 5 PM
> System: All Steam/Condensate Return
> Duration: 4 hours
> Reason: 
> 200 Lb Steam leak in hallway near 16 and 26 transition.
> 
> Effect: 
> Loss of high, medium and low pressure steam as well as condensate return
> in Bldg. 26. This means that no hot domestic water (for bathroom and
> kitchen sink faucets), hot lab process water (for lab sink faucets),
> heating hot water (building heat) or supply heating (via ceiling supply
> fans) will be operational during the 4-hour emergency shutdown period.
> 
> 