[69517] in Hotline Meeting
Bldg. 13 - Process Heating Hot Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 5 09:07:56 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71C44@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'elk@mit.edu'" <elk@MIT.Edu>, "'generoso@mit.edu'" <generoso@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>, "'src@mit.edu'" <src@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 5 Nov 2003 09:07:08 -0500
> To: B-Zone; Cust-Coach; elk@mit.edu; generoso@mit.edu; schedule@mit.edu;
> src@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 13 - Process Heating Hot Water Shutdown Request
>
>
The following process heating hot water (glycol) shutdown request for Bldg.
13 on Monday, November 10, 2003 is for your information and comment. Would
you please let me know whether this does or does not meet with your
approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 13
> Date: 11/10/2003
> Day: Monday
> Time: 6 AM - 9 AM
> System: Process Heating Hot Water (Glycol)
> Duration: 3 hours
> Reason:
> Tie-in service to new air handling unit for 1150.
>
> Effect:
> Loss of preheat to Air Handlers 1, 2, 3 and supply heating via ceiling
> supply fans to Bldg. 13 during the 3-hour shutdown period.
>
>