Bldg. 10 - Extended Chilled Water/Supply Cooling Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 29 10:40:02 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71BD1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
Cust-Coach
<cust-coach@mit.edu>,
"'dfucillo@mit.edu'" <dfucillo@mit.edu>,
"'dhelman@mit.edu'" <dhelman@mit.edu>,
"'emmarogers@mit.edu'"
<emmarogers@mit.edu>,
"'esdeb@mit.edu'" <esdeb@mit.edu>,
"'granvill@mit.edu'" <granvill@mit.edu>,
"'graposa@MIT.EDU'"
<graposa@mit.edu>,
"'jhlyons@mit.edu'" <jhlyons@mit.edu>,
"'jobrien@mit.edu'" <jobrien@mit.edu>,
"'jsoroko@mit.edu'"
<jsoroko@mit.edu>,
"'kates@mit.edu'" <kates@mit.edu>, "'lsc@mit.edu'"
<lsc@mit.edu>,
"'mdhinkle@mit.edu'" <mdhinkle@mit.edu>,
"'mleen@mit.edu'" <mleen@mit.edu>, "'ndk@mit.edu'" <ndk@mit.edu>,
"'rrhonda@mit.edu'" <rrhonda@mit.edu>, "'ryan@mit.edu'" <ryan@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'sdl-adm-lib@mit.edu'"
<sdl-adm-lib@mit.edu>,
"'tkeim@mit.edu'" <tkeim@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: Ronald Beaulieu <bobo@PLANT.MIT.EDU>,
"'shutdown@plant.mit.edu'"
<shutdown@PLANT.MIT.EDU>
Date: Wed, 29 Oct 2003 10:29:34 -0500
> To: C-Zone; Cust-Coach; Cust-Coach; dfucillo@mit.edu; dhelman@mit.edu;
> emmarogers@mit.edu; esdeb@mit.edu; granvill@mit.edu; graposa@MIT.EDU;
> jhlyons@mit.edu; jobrien@mit.edu; jsoroko@mit.edu; kates@mit.edu;
> lsc@mit.edu; mdhinkle@mit.edu; mleen@mit.edu; ndk@mit.edu;
> rrhonda@mit.edu; ryan@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> tkeim@mit.edu; shutdowns@mit.edu
> Cc: Ronald Beaulieu; shutdown@plant.mit.edu
> Subject: Bldg. 10 - Extended Chilled Water/Supply Cooling Shutdown
> Request
>
>
The following extended chilled water shutdown request for Bldg. 10 - 337,
358 and 359 on Thursday, 10/30/03 is for your information. Would you please
let me know whether this does or does not meet with your approval.
Thank you again for your time.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 10 - 337, 358 and 359
> Date: 10/30/2003
> Day: Thursday
> Time: 6 AM - 9 AM
> System: Chilled Water /Can isolate in 303
> Duration: 3 hours
> Reason:
> Replace isolation valves in 368.
>
> Effect:
> Loss of chilled water (air conditioning) and supply cooling via ceiling
> supply fans in 10 -337, 358 and 359 during the 3-hour shutdown period.
>
>