[69242] in Hotline Meeting
Bldg. E15 - Rescheduled Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 24 15:05:50 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71BB0@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Plant-Asbestos <plant-asbestos@mit.edu>,
Tim Donaghey
<TDonaghe@PLANT.MIT.EDU>,
"Joseph Vella, Jr." <jpvella@PLANT.MIT.EDU>,
"'barbra@media.mit.edu'" <barbra@media.mit.edu>,
E-Zone <E-Zone@mit.edu>,
"'haller@media.mit.edu'" <haller@media.mit.edu>,
"'heine@media.mit.edu'"
<heine@media.mit.edu>,
"'kdavis@media.mit.edu'" <kdavis@media.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'dcosta@mit.edu'"
<dcosta@mit.edu>,
"'johnnyd@mit.edu'" <johnnyd@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Operators
<Operators@PLANT.MIT.EDU>,
"'patriotabate@aol.com'"
<patriotabate@aol.com>
Date: Fri, 24 Oct 2003 15:03:50 -0400
> To: Plant-Asbestos; Tim Donaghey; Joseph Vella, Jr.;
> barbra@media.mit.edu; E-Zone; haller@media.mit.edu; heine@media.mit.edu;
> kdavis@media.mit.edu; shutdowns@mit.edu; dcosta@mit.edu; johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators;
> patriotabate@aol.com
> Subject: Bldg. E15 - Rescheduled Asbestos Removal Notification
>
>
The following rescheduled asbestos removal notification for Bldg. E15 - 040
is now for Wednesday, 11/12 AM to Thursday, 11/13 PM. If you have any
questions about this, please feel free to contact me either by return e-mail
or telephone.
Thank you again for your time.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E15 - 040
> Date: 11/12/2003
> Day: Wednesday
> Time: 7 AM (11/12) - 4 PM (11/13)
> System: None - asbestos removal noficiation
> Duration: 33 hours
> Reason:
> Must remove 120 square feet of floor tile and mastic.
>
> Effect:
> No access to E15 - 040 during the asbestos removal period.
>
>