[69100] in Hotline Meeting
Bldg. E40 - Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Oct 20 13:48:43 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71B4A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'aed@mit.edu'" <aed@mit.edu>, E-Zone <E-Zone@mit.edu>,
"'gwj@mit.edu'" <gwj@mit.edu>, "'jfob@mit.edu'" <jfob@mit.edu>,
"'jys@mit.edu'" <jys@mit.edu>, "'kelley@mit.edu'" <kelley@mit.edu>,
"'lambert@mitvma.mit.edu'" <lambert@mitvma.mit.edu>,
"'lrose@mit.edu'"
<lrose@mit.edu>,
"'mgibson@mit.edu'" <mgibson@mit.edu>,
"'pmosley@mit.edu'" <pmosley@mit.edu>,
"'schung@mit.edu'"
<schung@mit.edu>,
"'scottc@mit.edu'" <scottc@mit.edu>,
"'tdalton@mit.edu'" <tdalton@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 20 Oct 2003 13:44:59 -0400
> To: aed@mit.edu; E-Zone; gwj@mit.edu; jfob@mit.edu; jys@mit.edu;
> kelley@mit.edu; lambert@mitvma.mit.edu; lrose@mit.edu; mgibson@mit.edu;
> pmosley@mit.edu; schung@mit.edu; scottc@mit.edu; tdalton@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E40 - Building Power Shutdown Request
>
>
The following building power shutdown request for Bldg. E40 - Basement
Computer Room on Saturday, 10/25 is for your information and comment. Would
you please let me know whether this does or does not meet with your
approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E40 - Basement Computer Room
> Date: 10/25/2003
> Day: Saturday
> Time: 6 AM - 6 PM
> System: Building Power - Main Distribution Panel
> Duration: 12 hours
> Reason:
> Install and test new uninteruptable power supply in E40 - Basment Computer
> Room.
>
> Effect:
> Loss of building power in the above-mentioned area during the 12-hour
> shutdown period.
>
>