[68867] in Hotline Meeting
RE: Bldgs. E51 and E52 Rescheduled Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 10 10:49:34 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71AD8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'Barry Mendes'" <tr6@MIT.EDU>, Edward Moore <emoore@PLANT.MIT.EDU>,
Plant-Asbestos <plant-asbestos@MIT.EDU>, "'aed@mit.edu'" <aed@MIT.EDU>,
"'alterra@mit.edu'" <alterra@MIT.EDU>,
"'dori123@mit.edu'"
<dori123@MIT.EDU>, E-Zone <E-Zone@MIT.EDU>,
"'lhill@mit.edu'"
<lhill@MIT.EDU>,
"'lmorales@mit.edu'" <lmorales@MIT.EDU>,
"'mscoppa@mit.edu'" <mscoppa@MIT.EDU>,
"'shutdowns@MIT.EDU'"
<shutdowns@MIT.EDU>,
"'rberlin@mit.edu'" <rberlin@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'sdimond@mit.edu'"
<sdimond@MIT.EDU>,
"'wganger@mit.edu'" <wganger@MIT.EDU>,
"'gbrowne@mit.edu'" <gbrowne@MIT.EDU>,
"'graham@mit.edu'"
<graham@MIT.EDU>, "'gwj@mit.edu'" <gwj@MIT.EDU>,
"'mchin@mit.edu'"
<mchin@MIT.EDU>, "'mwf@mit.edu'" <mwf@MIT.EDU>,
"'scobb@mit.edu'"
<scobb@MIT.EDU>,
"'dcosta@mit.edu'" <dcosta@MIT.EDU>,
"'johnnyd@mit.edu'" <johnnyd@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
Operators
<Operators@PLANT.MIT.EDU>
Date: Fri, 10 Oct 2003 10:47:54 -0400
Dear Everyone:
The following rescheduled asbestos removal notification for Bldgs. E51 - E52
Cross-over
3rd floor on Friday, 11/3 at 5 PM to Sunday, 11/5 at 4 PM is again for your
information.
If you have any questions about this, please feel free to contact me either
by return e-mail or telephone.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
Status: Normal
Building: E51 and E52 - Cross-over - 3rd floor
Date: 11/3 - 5/03
Day: Friday, Saturday and Sunday
Time: 5 PM (11/3) - 4 PM (11/5)
System: None - asbestos removal notifiation only
Duration: 47 hours
Reason:
Must remove 630 square feet of asbestos in this area.
Effect: No access to E51 - E52 3rd floor cross-over during the asbestos
removal