[68856] in Hotline Meeting
Bldg 66 sub basement shutdown request for 10/15 - 10/17
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Oct 9 14:47:50 2003
Message-ID: <568F0AEE7A57D511923900508B55645136684A@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.EDU>, Cust-Coach <cust-coach@MIT.EDU>,
"'haverty@mit.edu'" <haverty@MIT.EDU>,
"'kkgleasn@mit.edu'"
<kkgleasn@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'swetzel@mit.edu'" <swetzel@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 9 Oct 2003 14:46:48 -0400
> To: A-Zone; Cust-Coach; haverty@mit.edu; kkgleasn@mit.edu;
> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg 66 sub basement shutdown request for 10/15 - 10/17
>
>
The following shutdown request is for building 66 sub-basement on 10/15-
10/17. Could you
please let me know if this does or does not meet with your approval?
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Normal
> Building: 66 sub-basement mech room
> Date: 10/15/2003
> Day: Wednesday
> Time: 6 am - 3 pm each day
> System: Smoke alarms
> Duration: 3 days
> Reason:
> Welding on the chilled water piping.
>
> Effect:
> The smoke detectors will be down during this time.
>
>