[68849] in Hotline Meeting
Bldg E19 Asbestos removal notification for 10/23
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Oct 9 10:14:03 2003
Message-ID: <568F0AEE7A57D511923900508B55645136683F@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: "'bengel@mit.edu'" <bengel@MIT.EDU>,
"'cschultz@mit.edu'"
<cschultz@MIT.EDU>,
"'dlking@mit.edu'" <dlking@MIT.EDU>,
"'donnab@MIT.EDU'" <donnab@MIT.EDU>, "'dreid@mit.edu'" <dreid@MIT.EDU>,
"'dshea@mit.edu'" <dshea@MIT.EDU>, "'dturn@mit.edu'" <dturn@MIT.EDU>,
E-Zone <E-Zone@MIT.EDU>, "'e19site@mit.edu'" <e19site@MIT.EDU>,
"'gwolf@mit.edu'" <gwolf@MIT.EDU>,
"'hallisey@mit.edu'"
<hallisey@MIT.EDU>,
"'ilf@mit.edu'" <ilf@MIT.EDU>, "'joconor@mit.edu'"
<joconor@MIT.EDU>,
"'kelley@mit.edu'" <kelley@MIT.EDU>,
"'kshooter@mit.edu'" <kshooter@MIT.EDU>,
"'lharris@MIT.EDU'"
<lharris@MIT.EDU>,
"'mbowers@mit.edu'" <mbowers@MIT.EDU>, "'mjk@mit.edu'" <mjk@MIT.EDU>,
Michael Sherman <MSherman@PLANT.MIT.EDU>,
Mary Tobin <mtobin@PLANT.MIT.EDU>,
"'narbonne@MIT.EDU'"
<narbonne@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'rberlin@mit.edu'" <rberlin@MIT.EDU>, RM-Org <rm-org@MIT.EDU>,
"'tquinn@mit.edu'" <tquinn@MIT.EDU>,
"'wbarrett@mit.edu'"
<wbarrett@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 9 Oct 2003 10:12:21 -0400
> To: bengel@mit.edu; cschultz@mit.edu; dlking@mit.edu; donnab@MIT.EDU;
> dreid@mit.edu; dshea@mit.edu; dturn@mit.edu; E-Zone; e19site@mit.edu;
> gwolf@mit.edu; hallisey@mit.edu; ilf@mit.edu; joconor@mit.edu;
> kelley@mit.edu; kshooter@mit.edu; lharris@MIT.EDU; mbowers@mit.edu;
> mjk@mit.edu; Michael Sherman; Mary Tobin; narbonne@MIT.EDU;
> opsnote@mit.edu; rberlin@mit.edu; RM-Org; tquinn@mit.edu;
> wbarrett@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg E19 Asbestos removal notification for 10/23
>
>
The following asbestos removal is scheduled for building E19 ground floor
stock room on 10/23/03. This notification is for your information.
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Normal
> Building: E19 ground floor stockroom
> Date: 10/23/2003
> Day: Thursday
> Time: 7 am - 3pm
> System: Asbestos removal
> Duration: 8 hours
> Reason:
> Pipe insulation is falling apart.
>
> Effect:
> The area will be cordoned off during the asbestos removal period.
>
>