[68677] in Hotline Meeting
Bldg. 66 - Revised Asbestos REmoval Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 2 13:37:08 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71AB4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "Joseph Vella, Jr." <jpvella@PLANT.MIT.EDU>,
Richard Hadge
<rhadge@PLANT.MIT.EDU>,
Plant-Asbestos <plant-asbestos@mit.edu>, A-Zone
<A-Zone@mit.edu>,
Cust-Coach <cust-coach@mit.edu>,
"'haverty@mit.edu'"
<haverty@mit.edu>,
"'kkgleasn@mit.ed'" <kkgleasn@mit.ed>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'swetzel@mit.edu'"
<swetzel@mit.edu>,
"'shutdown@mit.edu'" <shutdown@mit.edu>,
"'dcosta@mit.edu'" <dcosta@mit.edu>,
"'johnnyd@mit.edu'"
<johnnyd@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Operators
<Operators@PLANT.MIT.EDU>,
"'patriotabate@aol.com'"
<patriotabate@aol.com>
Date: Thu, 2 Oct 2003 13:31:08 -0400
> To: Joseph Vella, Jr.; Richard Hadge; Plant-Asbestos; A-Zone;
> Cust-Coach; haverty@mit.edu; kkgleasn@mit.edu;; schedule@mit.edu;
> swetzel@mit.edu; shutdowns@mit.edu; dcosta@mit.edu; johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators;
> patriotabate@aol.com
> Subject: Bldg. 66 - Revised Asbestos REmoval Notification
>
>
The following revied asbestos removal notificationf or Bldg. 66 - 1st, 3rd,
4th and 5th floors now at 5 PM on Friday, October 3 to 12 Noon on Sunday,
October 5 is for your information. If you have any questions about this,
please feel free to contact me either by return e-mail or telephone.
Thank you again.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 66 - 1st, 3rd 4th and 5th floors
> Date: 10/3/2003
> Day: Friday
> Time: 5 PM (10/3) - 12 Noon or so on Sunday, 10/5
> System: None - asbestos removal notification
> Duration: 43 hours
> Reason:
> Must remove and replace 400 (changed from 200) square feet (patches of
> floor tiles and mastic) in the above-listed areas.
>
> Effect:
> Each area will be cordoned off during the asbestos removal period.
>
>