Bldg. 1 - Air Handler Units 3 and 4 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 16 12:33:51 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D71987@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
        "'patdixon@mit.edu'"
	 <patdixon@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 16 Sep 2003 12:32:51 -0400

> To: 	C-Zone; Cust-Coach; shutdowns@mit.edu; patdixon@mit.edu;
> schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 1 - Air Handler Units 3 and 4 Shutdown Request
> 
> 
The following air handler units 3 and 4 shutdown request for Bldg. 1 - 235
and 390 on Tuesday, September 23 is for your review and comment.  Would you
please let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 1 - 235 and 390
> Date: 9/23/2003
> Day: Tuesday
> Time: 5 AM - 9 AM
> System: Air Handler Units 3 and 4
> Duration: 4 hours
> Reason: 
> Control System Upgrade.
> 
> Effect: 
> Loss of supply ventilation and supply cooling in 1 - 390 and 235. Loss of
> automatic control and monitoring by the Operations Center of Chilled Water
> (will not be shutdown in Bldg. 1 during the shutdown period.)
> 
> 