[68262] in Hotline Meeting
Bldg. 18 - Approved Smoke Detector Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Sep 15 10:19:26 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71971@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-Fire-Prot-Team <rm-fire-prot-team@MIT.EDU>, A-Zone <A-Zone@MIT.EDU>,
"'chemistryhq@mit.edu'" <chemistryhq@MIT.EDU>,
Cust-Coach
<cust-coach@MIT.EDU>, "'lhowe@mit.edu'" <lhowe@MIT.EDU>,
"'serotek@mit.edu'" <serotek@MIT.EDU>,
"'swade@mit.edu'" <swade@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'johnnyd@mit.edu'"
<johnnyd@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>,
"'rdevito@linbeck.com'" <rdevito@linbeck.com>
Date: Mon, 15 Sep 2003 10:18:30 -0400
> To: RM-Fire-Prot-Team; A-Zone; chemistryhq@mit.edu; Cust-Coach;
> lhowe@mit.edu; serotek@mit.edu; swade@mit.edu; shutdowns@mit.edu;
> johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Billy Homeyer;
> rdevito@linbeck.com
> Subject: Bldg. 18 - Approved Smoke Detector Shutdown
>
>
The following approved smoke detector shutdown for Bldg. 18 - All; basement
on Tuesday, September 16, 2003 is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 18 - All, basement
> Date: 9/16/2003
> Day: Tuesday
> Time: 7:30 AM - 2:30 PM
> System: Smoke Detectors
> Duration: 7 hours
> Reason:
> Construction duct; removal of doors to tunnels.
>
> Effect:
> Loss of smoke detectors in all of Bldg. 18 during the shutdown period.
>
>