[68082] in Hotline Meeting
Approved shutdown for buildings W71, W84, and W85 on 9/9 & 9/10
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Sep 8 13:01:57 2003
Message-ID: <568F0AEE7A57D511923900508B55645136673B@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: Vaughn Crayton <VCrayton@PLANT.MIT.EDU>, D-Zone <D-Zone@mit.edu>,
RM-PipeSys <rm-pipesys@mit.edu>, Warren Scott <WScott@PLANT.MIT.EDU>,
"'johnnyd@mit.edu'" <johnnyd@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Date: Mon, 8 Sep 2003 13:00:26 -0400
> To: Vaughn Crayton; D-Zone; RM-PipeSys; Warren Scott; johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; shutdowns@mit.edu
> Subject: Approved shutdown for buildings W71, W84, and W85 on 9/9 &
> 9/10
>
>
The following approved shutdown for building W71, W84 and W85 on 9/9 and
9/10 is for your information.
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Critical
> Building: W71, W84 and W85
> Date: 9/9/2003
> Day: Tuesday
> Time: 9/9 10 am - 9/10 1 am
> System: All steam and condensate
> Duration: 10 hours
> Reason:
> To tie in expansion joints in manhole 1022
>
> Effect:
> There will be a loss of hot domestic water, heating hot water, supply air
> heating, high, medium and low pressure steam and condensate return during
> this time.
>
>