Bldgs W71, W84 and W85 critical shutdown request for 9/9 & 9/10
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Sep 8 10:10:37 2003
Message-ID: <568F0AEE7A57D511923900508B556451366735@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: "'kcn@mit.edu'" <kcn@mit.edu>, "'mlieberm@mit.edu'" <mlieberm@mit.edu>,
"'mwhelan@mit.edu'" <mwhelan@mit.edu>,
"'rberlin@mit.edu'"
<rberlin@mit.edu>,
"'wganger@mit.edu'" <wganger@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
Schedules Office
<schedules@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 8 Sep 2003 10:07:32 -0400
> To: kcn@mit.edu; mlieberm@mit.edu; mwhelan@mit.edu; rberlin@mit.edu;
> wganger@mit.edu; shutdowns@mit.edu; Schedules Office
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs W71, W84 and W85 critical shutdown request for 9/9 &
> 9/10
>
>
The following shutdown request is for buildings W71, W84 and W85 on 9/9 &
9/10. Could you please let me know if this does or does not meet with your
approval?
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Critical
> Building: W71, W84, and W85
> Date: 9/9/2003
> Day: Tuesday
> Time: 9/9 10 am - 9/10 1 am
> System: All steam and condensate
> Duration: 10 hours
> Reason:
> To tie in expansion joints in the manhole 1022.
>
> Effect:
> There will be a loss of hot domestic water, heating hot water, supply air
> heating, high, medium and low pressure steam and condensate return during
> this time.
>
>