[67937] in Hotline Meeting
Bldg. 66 CV1 and CV2 Pumps Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Sep 4 15:07:20 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D718FF@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.EDU>, Cust-Coach <cust-coach@MIT.EDU>,
"'haverty@mit.edu'" <haverty@MIT.EDU>,
"'kkgleasn@mit.edu'"
<kkgleasn@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'swetzel@mit.edu'" <swetzel@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'dcosta@mit.edu'" <dcosta@MIT.EDU>,
"'johnnyd@mit.edu'" <johnnyd@MIT.EDU>,
"'crendog@mit.edu'"
<crendog@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
Operators
<Operators@PLANT.MIT.EDU>
Date: Thu, 4 Sep 2003 15:04:55 -0400
> To: A-Zone; Cust-Coach; haverty@mit.edu; kkgleasn@mit.edu;
> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu; dcosta@mit.edu;
> johnnyd@mit.edu; crendog@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: Bldg. 66 CV1 and CV2 Pumps Shutdown
>
>
The followng CV1 and CV2 Pumps shutdown for Bldg. 66 - building wide on 9/4
is for your information. If you have any questions about this, please
contact Kevin Creney at x2-1498.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 66 - entire building
> Date: 9/4/2003
> Day: Thursday
> Time: 7:30 AM - unknown
> System: CV1 and CV2 pumps
> Duration: unknown
> Reason:
> Contractor did not complete work.
>
> Effect:
> Loss of perimeter heat during unknown shutdown period.
>
>