Bldg. 66 CV1 and CV2 Pumps Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Sep 4 15:07:20 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D718FF@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.EDU>, Cust-Coach <cust-coach@MIT.EDU>,
        "'haverty@mit.edu'" <haverty@MIT.EDU>,
        "'kkgleasn@mit.edu'"
	 <kkgleasn@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'swetzel@mit.edu'" <swetzel@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'dcosta@mit.edu'" <dcosta@MIT.EDU>,
        "'johnnyd@mit.edu'" <johnnyd@MIT.EDU>,
        "'crendog@mit.edu'"
	 <crendog@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
        Operators
	 <Operators@PLANT.MIT.EDU>
Date: Thu, 4 Sep 2003 15:04:55 -0400 

> To: 	A-Zone; Cust-Coach; haverty@mit.edu; kkgleasn@mit.edu;
> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu; dcosta@mit.edu;
> johnnyd@mit.edu; crendog@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: 	Bldg. 66 CV1 and CV2 Pumps Shutdown
> 
> 
The followng CV1 and CV2 Pumps shutdown for Bldg. 66 - building wide on 9/4
is for your information. If you have any questions about this, please
contact Kevin Creney at x2-1498.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 66 - entire building
> Date: 9/4/2003
> Day: Thursday
> Time: 7:30 AM - unknown
> System: CV1 and CV2 pumps
> Duration: unknown
> Reason: 
> Contractor did not complete work.
> 
> Effect: 
> Loss of perimeter heat during unknown shutdown period.
> 
> 