[67923] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 6 - Air Handler/Supply Fan 4 Rescheduled Shutdown/Filter Ch

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Sep 4 09:29:15 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D718F4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@mit.edu>, "'chemistryhq@mit.edu'" <chemistryhq@mit.edu>,
        Cust-Coach <cust-coach@mit.edu>, "'ghughes@mit.edu'" <ghughes@mit.edu>,
        "'glabonte@mit.edu'" <glabonte@mit.edu>,
        "'khewitt@mit.edu'"
	 <khewitt@mit.edu>,
        "'mhankin@mit.edu'" <mhankin@mit.edu>,
        "'rhasselt@MIT.EDU'" <rhasselt@mit.edu>,
        "'rrdasari@mit.edu'"
	 <rrdasari@mit.edu>,
        "'saraf@mit.edu'" <saraf@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'serotek@mit.edu'"
	 <serotek@mit.edu>,
        "'swade@mit.edu'" <swade@mit.edu>,
        "'heatherg@mit.edu'" <heatherg@mit.edu>,
        "'zqueen@mit.edu'"
	 <zqueen@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 4 Sep 2003 09:28:19 -0400 

> To: 	C-Zone; chemistryhq@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; khewitt@mit.edu; mhankin@mit.edu; rhasselt@MIT.EDU;
> rrdasari@mit.edu; saraf@mit.edu; schedule@mit.edu; serotek@mit.edu;
> swade@mit.edu; heatherg@mit.edu; zqueen@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 6 - Air Handler/Supply Fan 4 Rescheduled
> Shutdown/Filter Change Request
> 
> 
Dear Everyone:

The following rescheduled air handler/supply fan 4  shutdown/filter change
for Bldg. 6 - 3rd and 4th floor labs now on Monday, September 8 is again for
your review and comment.  Would you please let me know whether this new date
does or does not meet with your approval.

Thanks very much.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 6 - 3rd and 4th floor labs
> Date: 9/8/2003
> Day: Monday
> Time: 8:30 AM - 9:30 AM
> System: Air Handler/Supply Fan 4 - PM#731106
> Duration: 1 hour
> Reason: 
> Box filter changes and fan belt changes.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in the
> above-mentioned areas during the 1-hour shutdown/filter change period.
> 
> 