Bldg. 39 - Critical Air Handlers 1 and 2 Supply Air Shutdown Requ

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Sep 3 09:22:40 2003

Message-ID: <568F0AEE7A57D511923900508B55645103D718D9@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'armay@mit.edu'" <armay@MIT.EDU>, B-Zone <B-Zone@MIT.EDU>,
        Cust-Coach
	 <cust-coach@MIT.EDU>, George Mac Leod <gmacleod@MIT.EDU>,
        "'mcgrath@mtl.mit.edu'" <mcgrath@mtl.mit.edu>,
        "'rcf@space.mit.edu'"
	 <rcf@space.mit.edu>,
        "'walsh@mtl.mit.edu'" <walsh@mtl.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 3 Sep 2003 09:22:26 -0400 

> To: 	armay@mit.edu; B-Zone; Cust-Coach; George Mac Leod;
> mcgrath@mtl.mit.edu; rcf@space.mit.edu; walsh@mtl.mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 39 - Critical Air Handlers 1 and 2 Supply Air Shutdown
> Request
> 
> 
The following Critical air handlers 1 and 2 supply air shutdown request for
Bldg. 39 - 301East and Clean Rooms and 301 West and Clean Rooms on Saturday,
September 6 is for your information.  Would you please let me know whether
this does or does not meet with your approval.

Thanks very much.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 39 - room 301 East and Clean Rooms and 301 West and Clean Rooms
> Date: 9/6/2003
> Day: Saturday
> Time: 7 AM - 3 PM
> System: Air Handlers 1 and 2
> Duration: 8 hours
> Reason: 
> Need to install newer variable speed drives for Air Handlers 1 and 2 (to
> control static duct pressure).
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in the
> above-mentioned areas during the shutdown epriod.
> 
> 