Bldg. 36 - All Steam Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Aug 29 11:52:28 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D718AB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, Robert Cunkelman <rpc@PLANT.MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'wrgibbs@rle.mit.edu'"
<wrgibbs@rle.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 29 Aug 2003 11:50:54 -0400
> To: amcgurl@rle.mit.edu; B-Zone; Cust-Coach; Robert Cunkelman;
> schedule@mit.edu; wrgibbs@rle.mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 36 - All Steam Shutdown Request
>
>
The following all steam shutdown request for Bldg. 36 on Thursday, September
4 is for your review and comment. Would you please let me know whether this
does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 36 - All Steam
> Date: 9/4/2003
> Day: Thursday
> Time: 8 AM - 2 PM
> System: All Steam
> Duration: 6 hours
> Reason:
> Repair steam leak to domestic hot water converter.
>
> Effect:
> Loss of hot domestic water in Bldg. 36. This means there will be no
> bathroom, kitchen or lab sink faucets will be operational during the
> shutdown period.
>
>