[67598] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 56 - Rescheduled Heating Hot Water/Condensate Return Shutdo

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 20 21:09:24 2003

Message-ID: <568F0AEE7A57D511923900508B556451023F24DC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jmganno@mit.edu'" <jmganno@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        A-Zone
	 <A-Zone@mit.edu>, "'bengel@mit.edu'" <bengel@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Date: Wed, 20 Aug 2003 11:59:32 -0400

> To: 	jmganno@mit.edu
> Cc: 	shutdown@plant.mit.edu; A-Zone; bengel@mit.edu; shutdowns@mit.edu
> Subject: 	Bldg. 56 - Rescheduled Heating Hot Water/Condensate Return
> Shutdown
> 
> 
Dear Jack,

It has been requested the heating hot water/condensate return shutdown for
Bldg. 56 - 851 and 860 be reschedule to Tuesday, August 26.  Would you
please let me know whether this new date meets with your approval or does
not.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 56 - 851 and 860
> Date: 8/26/2003
> Day: Tuesday
> Time: 7:30 AM - 3 Pm
> System: Heating (reheat) Hot Water/Condensate Return (Humidifier)
> Duration: 7.5 hours
> Reason: 
> Replace valves.
> 
> Effect: 
> Loss of heating hot water (building heat) and condensate water (humidifyer
> steam) during the shutdown period in 56 - 851 and 860 only.
> 
> 

home help back first fref pref prev next nref lref last post