Bldg 4 shutdown request for 8/22

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Aug 20 02:03:09 2003

Message-ID: <568F0AEE7A57D511923900508B55645103B602FE@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@plant.mit.edu>
To: adoran@mit.edu, bales@mit.edu, C-Zone <C-Zone@mit.edu>,
        chemistryhq@mit.edu, cod@mit.edu, frc@mit.edu, ghughes@mit.edu,
        glabonte@mit.edu, glwilson@mit.edu, graham@mit.edu, jcentor@mit.edu,
        lechtman@mit.edu, lhowe@mit.edu, lkn@mit.edu, mhankin@mit.edu,
        rberlin@mit.edu, rrhonda@mit.edu, schedule@mit.edu, serotek@mit.edu,
        staton@mit.edu, swade@mit.edu, umans@mit.edu, wganger@mit.edu,
        shutdowns@mit.edu
Cc: shutdown@plant.mit.edu, rm-shutdown@mit.edu
Date: Tue, 19 Aug 2003 11:33:42 -0400

> To: 	adoran@mit.edu; bales@mit.edu; C-Zone; chemistryhq@mit.edu;
> cod@mit.edu; frc@mit.edu; ghughes@mit.edu; glabonte@mit.edu;
> glwilson@MIT.EDU; graham@mit.edu; jcentor@mit.edu; lechtman@mit.edu;
> lhowe@mit.edu; lkn@mit.edu; mhankin@mit.edu; rberlin@mit.edu;
> rrhonda@mit.edu; schedule@mit.edu; serotek@mit.edu; staton@mit.edu;
> swade@mit.edu; umans@MIT.EDU; wganger@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: 	Bldg 4 shutdown request for 8/22
> 
> 
The following shutdown request is for building 4 rooms 032, 034, 036, 040,
044, 046, and 052 on 8/22/03.  Could you please let me know if this does or
does not meet with your approval?

Thank you
Dawn Simonelli
Repair and Maintenance


> Status: Normal
> Building: Bldg 4 rooms 032, 034, 036, 040, 044, 046, and 052
> Date: 8/22/2003
> Day: Friday
> Time: 6 am - 8:30 am 
> System: Chilled water
> Duration: 2 1/2 hours
> Reason: 
> To tie in to the chilled water piping in 046 for service to the new fan
> coil unit on the first floor.  
> 
> Effect: 
> There will be a loss of chilled water during this time.  
> 
> 