[67546] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg 18 elevator shutdown for 8/19 - 8/22

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Aug 18 14:42:12 2003

Message-ID: <568F0AEE7A57D511923900508B55645103B602D0@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: RM-ElecCtl <rm-elecctl@mit.edu>, Billy Homeyer
	 <whomeyer@PLANT.MIT.EDU>,
        Joseph Collins <JCollins@PLANT.MIT.EDU>, A-Zone <A-Zone@mit.edu>,
        chemistryhq@mit.edu, Cust-Coach
	 <cust-coach@mit.edu>, lhowe@mit.edu,
        serotek@mit.edu, swade@mit.edu, schedule@mit.edu, shutdowns@mit.edu,
        johnnyd@mit.edu
Cc: shutdown@PLANT.MIT.EDU, rm-shutdown@mit.edu
Date: Mon, 18 Aug 2003 14:42:08 -0400

> To: 	RM-ElecCtl; Billy Homeyer; Joseph Collins; A-Zone;
> chemistryhq@mit.edu; Cust-Coach; lhowe@mit.edu; serotek@mit.edu;
> swade@mit.edu; schedule@mit.edu; shutdowns@mit.edu; johnnyd@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: 	Bldg 18 elevator shutdown for 8/19 - 8/22
> 
> 
The following shutdown for building 18 elevators on 8/19 - 8/22 is for your
information. 

Thank you
Dawn Simonelli
Repair and Maintenance


> Status: Normal
> Building: 18 passenger elevators
> Date: 8/19/2003
> Day: Tuesday
> Time: 8/19 7 am - 3 pm 8/22
> System: Passenger elevators
> Duration: 4 days
> Reason: 
> Painting the doors and the frames on all floors.  Elevator #1Tuesday and
> Wenesday, elevator 2 on Thursday and Friday.
> 
> Effect: 
> Each elevator will be down for 2 days.
> 
> 