[67543] in Hotline Meeting
Bldg 56 shutdown request for 8/25/03
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Aug 18 10:22:35 2003
Message-ID: <568F0AEE7A57D511923900508B55645103B602A0@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.EDU>, aglomski@MIT.EDU, bengel@MIT.EDU,
chemistryhq@MIT.EDU, cpoon@MIT.EDU, Cust-Coach <cust-coach@MIT.EDU>,
cwolfson@MIT.EDU, dudley@MIT.EDU, jmganno@MIT.EDU, johnnyd@MIT.EDU,
kkgleasn@MIT.EDU, lhowe@MIT.EDU, lsc@MIT.EDU, mjudge@MIT.EDU,
nsteele@MIT.EDU, rha@MIT.EDU, schedule@MIT.EDU, serotek@MIT.EDU,
swetzel@MIT.EDU, tquinn@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 18 Aug 2003 10:22:18 -0400
> To: A-Zone; aglomski@mit.edu; bengel@mit.edu; chemistryhq@mit.edu;
> cpoon@mit.edu; Cust-Coach; cwolfson@mit.edu; dudley@mit.edu;
> jmganno@mit.edu; johnnyd@mit.edu; kkgleasn@mit.edu; lhowe@mit.edu;
> lsc@mit.edu; mjudge@mit.edu; nsteele@mit.edu; rha@mit.edu;
> schedule@mit.edu; serotek@mit.edu; swetzel@mit.edu; tquinn@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg 56 shutdown request for 8/25/03
>
>
The following shutdown request is for building 56 rooms 851 and 860 on
8/25/03. Could you please let me know if this does or does not meet with
your approval?
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Normal
> Building: 56 rooms 851 and 860
> Date: 8/25/2003
> Day: Monday
> Time: 7: 30 am - 3 pm
> System: Reheat hot water, and humidity steam valve.
> Duration: 7 1/2 hours
> Reason:
> Repalcing valves.
>
> Effect:
> There will be a loss of heating hot water and condensate returns during
> this time.
>
>