Bldg. 13 - Fan Exhaust Hoods/Air Handler /Supply Fan 8 Preventive
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Aug 15 15:27:09 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F24D1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'elk@mit.edu'" <elk@MIT.Edu>, "'generoso@mit.edu'" <generoso@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>, "'src@mit.edu'" <src@MIT.Edu>,
"shutdowns (E-mail)" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 15 Aug 2003 15:27:07 -0400
> To: B-Zone; Cust-Coach; elk@mit.edu; generoso@mit.edu; schedule@mit.edu;
> src@mit.edu; shutdowns (E-mail)
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 13 - Fan Exhaust Hoods/Air Handler /Supply Fan 8
> Preventive Maintenance Shutdown Request
>
>
The following fan exhaust hoods/Air Handler/Supply Fan 8 preventive
maintenance shutdown request for Bldg. 13 - 5137, 5119, 5108, 4100, 5072
and 5076 on Thursday, 8/21 is for your review and comment. Would you please
let either me or Dawn Simonelli know whether this does or does not meet with
your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 13 - 5137, 5119, 5108, 4100, 5072 and 5076
> Date: 8/21/2003
> Day: Thursday
> Time: 7:30 AM - 3:30 PM
> System: Air Handler/Supply Fan 8 and Fan Exhaust Hoods
> Duration: 8 hours
> Reason:
> Preventive Maintenance work.
>
> Effect:
> Loss of supply cooling and supply heating in PM#717352 (Air Handler/Supply
> Fan 8; Loss of fan exhaust Hoods/exhaust laboratory air in 5119 -
> PM#701769; 5108 - PM#701766; 4100 - PM#701770; 4100 - PM#701765; 5072 -
> PM# 701782 - 1 hood in 5072 and 1 in 5076. Each unit will be down for
> approximately 50 minutes while ther other units remain operational.
>
>