Bldgs. E18 and E19 Domestic and Lab Process Water Shutdown Reques

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Aug 8 14:01:06 2003

Message-ID: <568F0AEE7A57D511923900508B556451023F2451@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-CarpCon <rm-carpcon@mit.edu>, RM-StrcPnt <rm-strcpnt@mit.edu>,
        RM-ElecCtl <rm-elecctl@mit.edu>, "'bengel@mit.edu'" <bengel@mit.edu>,
        "'dreid@mit.edu'" <dreid@mit.edu>, "'dudley@mit.edu'" <dudley@mit.edu>,
        E-Zone <E-Zone@mit.edu>, "'jmganno@mit.edu'" <jmganno@mit.edu>,
        "'nsteele@mit.edu'" <nsteele@mit.edu>,
        "'safety@mit.edu'"
	 <safety@mit.edu>,
        "'sdalton@mit.edu'" <sdalton@mit.edu>,
        "'tquinn@mit.edu'" <tquinn@mit.edu>, "'wardd@mit.edu'" <wardd@mit.edu>,
        "'cschultz@mit.edu'" <cschultz@mit.edu>,
        "'dlking@mit.edu'"
	 <dlking@mit.edu>,
        "'donnab@MIT.EDU'" <donnab@mit.edu>,
        "'dshea@mit.edu'"
	 <dshea@mit.edu>, "'dturn@mit.edu'" <dturn@mit.edu>,
        "'e19site@mit.edu'"
	 <e19site@mit.edu>,
        "'gwolf@mit.edu'" <gwolf@mit.edu>,
        "'hallisey@mit.edu'" <hallisey@mit.edu>, "'ilf@mit.edu'" <ilf@mit.edu>,
        "'joconor@mit.edu'" <joconor@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>,
        "'kshooter@mit.edu'" <kshooter@mit.edu>,
        "'lharris@MIT.EDU'" <lharris@mit.edu>,
        "'mbowers@mit.edu'"
	 <mbowers@mit.edu>, "'mjk@mit.edu'" <mjk@mit.edu>,
        RM-Support
	 <RM-Support@mit.edu>, "'lsanto@mit.edu'" <lsanto@mit.edu>,
        "'mcgreal@mit.edu'" <mcgreal@mit.edu>,
        "'joanf@mit.edu'" <joanf@mit.edu>,
        "'sfrankel@mit.edu'" <sfrankel@mit.edu>,
        "'narbonne@MIT.EDU'"
	 <narbonne@mit.edu>,
        "'opsnote@mit.edu'" <opsnote@mit.edu>,
        "'wbarrett@mit.edu'" <wbarrett@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 8 Aug 2003 14:00:58 -0400 

> To: 	RM-CarpCon; RM-StrcPnt; RM-ElecCtl; bengel@mit.edu; dreid@mit.edu;
> dudley@mit.edu; E-Zone; jmganno@mit.edu; nsteele@mit.edu; safety@mit.edu;
> sdalton@mit.edu; tquinn@mit.edu; wardd@mit.edu; cschultz@mit.edu;
> dlking@mit.edu; donnab@MIT.EDU; dshea@mit.edu; dturn@mit.edu;
> e19site@mit.edu; gwolf@mit.edu; hallisey@mit.edu; ilf@mit.edu;
> joconor@mit.edu; shutdowns@mit.edu; kshooter@mit.edu; lharris@MIT.EDU;
> mbowers@mit.edu; mjk@mit.edu; RM-Support; lsanto@mit.edu; mcgreal@mit.edu;
> joanf@mit.edu; sfrankel@mit.edu; narbonne@MIT.EDU; opsnote@mit.edu;
> wbarrett@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. E18 and E19 Domestic and Lab Process Water Shutdown
> Request
> 
> 
The following hot/ cold domestic water  and hot and cold lab process water
shutdown request for Bldgs. E18 and E19 on Saturday, August 16 is for your
review and comment.  Would your please let me know whether this does or does
not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872


> Status: Normal
> Building: E18 and E19
> Date: 8/16/2003
> Day: Saturday
> Time: 7 AM - 3 PM
> System: Hot/Cold Domestic and Lab Process Water
> Duration: 8 hours or longer
> Reason: 
> To repipe potable (lab process) water through 4" back flows for building
> continuity at City of Cambridge's request.
> 
> Effect: 
> Loss of hot/cold domestic water. This means that no toilets, bathroom,
> kitchen, lab sink faucets or drinking fountains will be operational. Loss
> of hot/cold lab process water. This means that no lab equipment requiring
> same will be operational during the shutdown period.
> 
> 